      January 13 – 16

Check mark Installed negative equalizer conduit
Check mark Installed 50 pair control cable within existing duct bank
Check mark Replaced negative cable between manholes
Check mark Installed tube shell enclosure
Check mark Removed existing signal and communication cables and brackets
Check mark Removed existing EA systems
Check mark Performed miscellaneous signal and track punch list work
Check mark Cleaned existing discharge line
Check mark Performed miscellaneous surveys and walkthrough
Check mark Commissioned communication cable