E subway
Weekend Work
in the 53 St Tubes
Nineteenth Weekend Completed
Check markWhat we accomplished
      October 7 – 10

Check mark Replaced deteriorated track ties
Check mark Replaced third rail and third rail protection board
Check mark Installed covers on new discharge line valves
Check mark Replaced various power, control and communications cables
Check mark Installed antenna cable brackets
Check mark Scraped, cleaned and painted fire line
Check mark Performed miscellaneous surveys, tests, and walkthrough
October 14 – 17: Next round of work