Fix&Fortify Sandy Recovery Work Planned Service Changes
E subway
Weekend Work
in the 53 St Tubes
Twentieth Weekend Completed
Check markWhat we accomplished
      October 14 – 17

Check mark Delivered circuit breaker house equipment
Check mark Pulled various cables through manholes
Check mark Installed miscellaneous antenna cable brackets
Check mark Installed discharge line valve covers
Check mark Scraped, cleaned, and painted fire line
Check mark Cleaned pump rooms
Check mark Completed signal and antenna punch list work items
Check mark Performed miscellaneous surveys, tests, and walk-through
 