Fix&Fortify Sandy Recovery Work Planned Service Changes
E subway
Weekend Work
in the 53 St Tubes
Fifth Weekend Completed
Check markWhat we accomplished
      March 4 - 7

Check mark Installed over 7,800 feet of new signal cable
Check mark Installed 8,200 feet of fiber optic cable
Check mark Installed 12,000 feet of communication cable
Check mark Installed 3,200 feet of antenna cable
Check mark Installed 200 brackets and clips
Check mark Performed tunnel surveys for upcoming weekend work
March 11 - 14: Next round of work