Weekend Work
in the 53 St Tubes
Twelfth Weekend Completed
Check markWhat we accomplished June 24 - 27

Check mark Installed seven emergency alarm assemblies
Check mark Installed five signal junction boxes
Check mark Pulled and installed 1,400 feet of positive cable from manhole on Roosevelt Island Substation to circuit breaker house
Check mark Secured 350 feet of cable to tunnel walls
Check mark Replaced 1,000 feet of track ties and plates
Check mark Replaced seven discharge line pump valve connections
Check mark Painted circuit breaker house walls and ceiling
Check mark Performed miscellaneous surveys