Fix&Fortify Sandy Recovery Work Planned Service Changes
E subway
Weekend Work
in the 53 St Tubes
Eleventh Weekend Completed
Check markWhat we accomplished June 17 - 20

Check mark Installed four emergency alarm assemblies
Check mark Installed two emergency telephone boxes
Check mark Installed new signal central instrument house (CIH) box
Check mark Installed 600 feet of fiber optic cable in pump room and substation
Check mark Secured 4,000 feet of cable to tunnel walls
Check mark Chopped 280 feet of concrete and removed old ties and plates
Check mark Replaced seven discharge line pump valve connections
Check mark Performed miscellaneous surveys
Check mark Tested 1,200 feet of antenna cable and 1,700 feet of fiber optic cable
June 24 – 27: Next round of work