Fix&Fortify Sandy Recovery Work Planned Service Changes
E subway
Weekend Work
in the 53 St Tubes
Thirteenth Weekend Completed
Check markWhat we accomplished July 29 – August 1

Check mark Installed 500 feet of antenna cable
Check mark Pulled and installed 1,800 feet of positive and negative cable from Roosevelt Island Substation manhole to circuit breaker house
Check mark Installed 70 feet of new communication cable
Check mark Installed 30 antenna brackets
Check mark Secured 2,250 feet of signal cable and 2,300 feet of communication cable to tunnel walls
Check mark Replaced five discharge line valves
Check mark Replaced 250 feet of track ties and plates
Check mark Inspected 700 feet of track, including rails, ties, and third rail hardware
Check mark Performed miscellaneous surveys and walk-through
August 5 – 8: Next round of work