Skip to main content
Go to MTA homepage
 
Fix&Fortify Sandy Recovery Work Planned Service Changes
E subway
Weekend Work
in the 53 St Tubes
Second Weekend Completed
Check markWhat we accomplished
      January 15 - 18

Check mark Installed 4,600 feet of new signal cable
Check mark Installed 90 wall brackets and clips for future signal installation

Check mark Installed 5,400 feet of antenna cable

Check mark Installed 900 antenna wall brackets and clips
Check mark Removed old cable and other equipment from circuit breaker house
Check mark Performed site surveys in preparation for upcoming tunnel work
February 5 - 8: Next round of work
  • Google Translate