Fix&Fortify Sandy Recovery Work Planned Service Changes
E subway
Weekend Work
in the 53 St Tubes
Fifteenth Weekend Completed
Check markWhat we accomplished
      August 19 – 22

Check mark Removed and installed tube shell protection conduit and cable
Check mark Installed battery cable and steel support for brackets in circuit breaker houses
Check mark Poured concrete around new discharge line valve
Check mark Terminated and tested cables
Check mark Installed transition bones/brackets to support conduits
Check mark Scraped and painted file line
Check mark Performed miscellaneous surveys, tests, and walkthrough
September 9– 12: Next round of work