Fix&Fortify Sandy Recovery Work Planned Service Changes
E subway
Weekend Work
in the 53 St Tubes
Seventh Weekend Completed
Check markWhat we accomplished
      Apr 8 - 11

Check mark Installed 7,200 feet of new signal cable
Check mark Installed 6,700 feet of power cable
Check mark Installed 5,300 feet of communication cable
Check mark Installed 350 feet of antenna cable
Check mark Replaced an additional 700 feet of cable
Check mark Installed 680 cable supports and brackets
Check mark Installed 4,600 feet of inner duct
Check mark Performed surveys for upcoming weekend work
May 13 – 16: Next round of work