Weekend Work in the 53 St Tubes
First Weekend Completed
Check markWhat we accomplished October 9 - 12
 
Check mark Installed temporary lights on tracks and at emergency shafts
Check mark Removed debris from tracks
Check mark Installed 550 wall brackets for future cable installation
Check mark Installed and tensioned 345 feet of cable
Check mark Removed 2,000 feet of old cable from manholes
Check mark Cleaned 1,600 feet of ductbanks
Check mark Surveyed field conditions for new signal installations
• October 16 - 19: Next round of work