Weekend Work in the 53 St Tubes
Fourth Weekend Completed
Check markWhat we accomplished November 20-23
 
Check mark Installed and tensioned 1,300 feet of cable
Check mark Installed 5,700 feet of new antenna cable
Check mark Installed 100 wall brackets to support future signal installation
Check mark Installed 500 antenna brackets and clips
Check mark Removed 500 feet of old battery control cables
Check mark Cleaned 3,200 feet of ducts
Check mark Performed site surveys