Weekend Work
Twenty-first Weekend Completed
Check markWhat we accomplished
      September 30 – October 3
 

Check mark Secured and covered 1,750 feet of previously installed signal cable bundles
Check mark Installed equipment and boxes at mid-river pump rooms
Check mark Installed 2,035 feet of signal conduit
Check mark Installed 480 feet of heat tracing system cable
Check mark Patched over newly installed negative rail conduits
Check mark Spliced cables and radio antennas
Check mark Drilled rails for negative cable installation
Check mark Installed and secured communication cable
Check mark Installed cable connectors
Check mark Performed testing of various cables
Next round of work: October 7 – 10