Fix&Fortify Sandy Recovery Work Planned Service Changes
A subwayC subway
Weekend Work
Twentieth Weekend Completed
Check markWhat we accomplished
     September 23 - 26
 

Check mark Secured and covered 1,615 feet of previously installed signal cable bundle
Check mark Installed access hatch at mid-river pump room
Check mark Installed 940 feet of fiber optic cable
Check mark Installed 2,642 feet of signal cable
Check mark Installed 435 feet of signal conduit
Check mark Spliced ventilation fan control and other cables
Check mark Installed 380 feet of negative cables at cable section manholes
Check mark Installed 400 feet of equalizer cables
Check mark Installed 150 feet of tube shell drain cable
Check mark Installed 400 feet of radio antenna cable
Check mark Installed cable connectors
Check mark Installed 300 feet of heat tracing system cable
Check mark Painted fan plant electrical distribution rooms and fluid area
Next round of work: September 30 – October 3 