Fix&Fortify Sandy Recovery Work Planned Service Changes
A subway
Weekend Work
Seventh Weekend Completed
Check markWhat we accomplished
     March 18 - 21
 

Check mark Installed 1,450 feet of communication cable
Check mark Installed 12,250 feet of fiber optic cable
Check mark Installed 3,300 feet of Emergency Alarm/Emergency Telephone signal cable
Check mark Installed new insulation and replaced damper bearings in the Front Street fan plant
Check mark Installed 395 feet of conduit
Check mark Removed duct blockages
Check mark Repaired 290 square feet of the tube liner
April 1- 4: Next round of work