Fix&Fortify Sandy Recovery Work Planned Service Changes
A subway
Weekend Work
Thirteenth Weekend Completed
Check markWhat we accomplished
     July 8 - 11
 

Check mark Installed 1,110 feet of fiber optic conduit and supports
Check mark Installed 3,500 feet of instrumentation and control cables for the mid-river pumps
Check mark Replaced existing equipment and materials (panels, switches, and conduit) at mid-river pump rooms
Check mark Installed nine Emergency Alarm/Emergency Telephone panels
Check mark Installed stress relief loop connections on radio antenna cable
Check mark Chopped concrete for negative and pump room conduit and cables
Check mark Spliced communication cables and shielded negative cables
Check mark Installed 970 feet of negative rail cable
July 15 - 18: Next round of work