Fix&Fortify Sandy Recovery Work Planned Service Changes
A subway
Weekend Work
Fourteenth Weekend Completed
Check markWhat we accomplished
     July 15 - 18
 

Check mark Installed 650 feet of fiber optic conduit and cable supports
Check mark Installed 8,900 feet of signal cable
Check mark Installed 150 feet of communications cable
Check mark Chopped concrete for positive cables and pump room conduit and cables
Check mark Spliced shielded negative cables
Check mark Installed 300 feet of negative rail cable
Check mark Installed 1,800 feet of instrumentation and control cables for the mid-river pumps
Check mark Performed communications cable testing
Check mark Installed 460 feet of conduit of various sizes throughout the project site
July 22 - 25: Next round of work