Fix&Fortify Sandy Recovery Work Planned Service Changes
A subway
Weekend Work
First Weekend Completed
Check markWhat we accomplished
     January 8 – 11
 

Check mark Grouted 150 square feet of existing concrete duct benches
Check mark Installed 770 feet of radio antenna cable
Check mark Installed 175 feet of messenger cable, the high-strength steel wire used to support suspended aerial cable, for future installation of communication cable
Check mark Relocated 3,400 feet of signal messenger cable
Check mark Prepared 8,800 feet of inner ducts for future cable installation
Check mark Installed 330 feet of conduit
Check mark Installed new telephone terminal box at one of the circuit breaker houses
Check mark Performed site survey of tunnel
January 15 - 18: Next round of work