Fix&Fortify Sandy Recovery Work Planned Service Changes
A subway
Weekend Work
Second Weekend Completed
Check markWhat we accomplished
     January 15 – 18
 

Check mark Grouted 44 square feet of existing concrete duct benches
Check mark Installed 994 feet of radio antenna cable
Check mark Installed 75 feet of messenger cable, the high-strength steel wire used to support suspended aerial cable, for future installation of communication cable
Check mark Relocated 2,150 feet of signal messenger cable
Check mark Installed 13,800 feet of power cable and 4,600 feet of grounding cable for new pumps
Check mark Installed five exhaust fans for fan plant HVAC system
Check mark Performed site survey of tunnel
February 5 - 8: Next round of work