2015 Line Work & Planned Service Changes

7 Weekend Work
Fourth Weekend Completed
Check markWhat we accomplished
     January 24 - 26
 

Check mark

Pulled an additional 4,120 feet of signal cable from Queensboro Plaza to 33 St

Check mark

Installed 13 new wayside radio unit antennas, power and fiber optic cable, and conduits for four WRUs

Check mark

Completed installation of 30 feet of discharge line insulation

Check mark

Pump room renovation included new valves as well as door and concrete floor replacement

Check mark

Pulled 8,400 feet of power cable

Check mark Installed 100-pair telecommunications cable
Check mark

Installed more than 500 feet of new eight-inch discharge line

Check mark

Removed 30 feet of old, ceiling-mounted six-inch discharge line and hangers

Check mark

Chopped concrete for future construction of new six- and eight-inch sump pump drainage inlet and piping

Check mark

Replaced track components, including 51 water damaged tie blocks and five water damaged stone ties, as well as third rail insulators and track tie plates

Check mark

Performed leak repair, including oil scouring and application of primer and final sealant

Check mark

Installed 320 feet of 500 MCM jumper cable

Check mark

Began work to remove more than 200 feet of six-inch discharge line

January 30 - February 2: Next round of work


2015 7 subway Line Weekend Work

In 2015, significant weekend work on three capital improvement projects on the 7 subway Line in Queens continues: installation of a new Communications-Based Train Control (CBTC) signal system; elevated track replacement and infrastructure work; and the reconstruction and fortification of the Steinway Tubes.

The majority of this work is scheduled over weekends when ridership is lower and gives our workers continuous, train-free access to the 7 subway Line. We are aware of the inconvenience these and other disruptions cause, and we appreciate your patience.

These projects will bring a modern, state-of-the-art signal system and reliable, resilient infrastructure upgrades to the
7 subway
Line.

Get more information about our work on the 7 subway Line, plus the full calendar of service changes, here.