Fix&Fortify Sandy Recovery Work Planned Service Changes
4 subway
Weekend Work
Seventeenth Weekend Completed
Check markWhat we accomplished
     September 9 – 12
 

Check mark
    Installed 3,500 feet of tunnel receptacle cable
Check mark Installed 2,396 feet of power supervisory control cable
Check mark Installed 5,976 feet of communication messenger brackets and cable
Check mark Installed 210 feet of conduit for FDNY sound powered telephones
Check mark Chemically grouted 926 feet of cracks in the concrete tube liner
Check mark Poured 2 cubic yards of concrete encasements around the steel structure for a new tunnel lighting room
Check mark Installed 42 tunnel lighting transition junction boxes
October 21 – 24: Next round of work