Weekend Work
Sixteenth Weekend Completed
Check markWhat we accomplished
     September 2 – 4
 

Check mark Installed 1,000 feet of radio antenna cable
Check mark Installed 10,470 feet of communication cable
Check mark Installed 2,350 feet of tunnel lighting cable
Check mark Installed 70 tunnel lighting junction boxes
Check mark Performed asbestos abatement
Check mark Ran conduit through existing utility tunnel for fiber optic communication cables
Check mark Installed concrete formwork and rebar and poured the concrete floor slab, landing, and stairs for new tunnel lighting room
Check mark Previous work for new tunnel lighting room included installation of concrete formwork and construction of steel structure
September 9 – 12: Next round of work