Fix&Fortify Sandy Recovery Work Planned Service Changes
4 subway
Weekend Work
Eighteenth Weekend Completed
Check markWhat we accomplished
     October 21 – 24
 

Check mark Installed tunnel lighting cable, junction boxes, and fixtures
Check mark Installed 1,600 feet of tunnel receptacle cable
Check mark Tensioned 2,670 feet of communication messenger cable
Check mark Installed 3,850 feet of copper communication cable
Check mark Installed conduits for traction power negative cable crossovers
Check mark Installed masonry wall for new tunnel lighting room
Check mark Replaced six pipe segments of the pump room discharge main
Check mark Installed 50 feet of conduit for pump room power and control cables
October 28 – 31: Next round of work