Fix&Fortify Sandy Recovery Work Planned Service Changes
4 subway
Weekend Work
Sixth Weekend Completed
Check markWhat we accomplished
     April 22 - 25
 

Check mark Injected chemical grouting to repair 547 feet of tunnel surface
Check mark Repaired 67 square feet of concrete duct bench
Check mark Installed 2,423 feet of brackets and cable for permanent tunnel lighting and receptacles
Check mark Installed 10,140 feet of temporary lighting
Check mark Drilled anchors for 4,650 feet of radio antenna brackets
May 13 - 16: Next round of work