Weekend Work
Thirty-sixth Weekend Completed
Check markWhat we accomplished
     February 16 – 19  
 

Check mark Installed 984 feet of antenna cable
Check mark Installed 19 Emergency Alarm brackets
Check mark Completed termination of six signal boxes
Check mark Installed 260 feet of conduit
Check mark Completed permanent strapping of 1,730 feet of communications cable
Check mark Installed 100 feet of conduit
Check mark Installed 3,930 feet of inner duct
Check mark Installed 18,000 feet of pump room feeders
Check mark Installed two permanent pumps
Check mark Installed four equipment panels
Check mark Installed 6,500 feet of fiber optic cable
Check mark Installed 970 feet of communications cable and 1,170 feet of miscellaneous cable
February 23 – 26: Next round of work