Weekend Work
Thirty-fifth Weekend Completed
Check markWhat we accomplished
     February 9 – 12  
 

Check mark Installed 320 feet of conduit
Check mark Installed 4,200 feet of communications cable
Check mark Installed 3,900 feet of power control cable
Check mark Completed signal equipment work
Check mark Completed cold shrink application over 31 antenna loops
Check mark Installed six assembly brackets and 54 feet of conduit for emergency alarms/telephones
Check mark Placed four permanent pumps and installed 92 feet of piping
Check mark Installed 2,600 feet of fiber optic cable
Check mark Installed seven pump room equipment panels
Check mark Replaced 48 feet of duct
Check mark Installed 190 feet of miscellaneous cable
Check mark Drilled two pump room cores
February 16 – 19: Next round of work