Weekend Work
Thirty-fourth Weekend Completed
Check markWhat we accomplished
     February 2 – 5  
 

Check mark Replaced 200 feet of tie blocks
Check mark Completed wiring of nine signal cases
Check mark Installed temporary motor control centers and drilled cores for additional panels
Check mark Installed 964 feet of cable  
Check mark Installed 147 feet of conduit
Check mark Installed 2,170 feet of control cable
Check mark Installed 4,640 feet of communications cable
Check mark Installed five riser boxes
Check mark Installed 1,360 straps for securing cable
Check mark Installed 650 feet of inner duct
Check mark Installed 10 emergency alarm boxes
February 9 – 12: Next round of work