Weekend Work
Thirty-third Weekend Completed
Check markWhat we accomplished
     January 26 – 29  
 

Check mark Installed 140 feet of conduit 
Check mark Installed 10,921 feet of copper communication cable  
Check mark Installation of 5,560 feet of control cable 
Check mark Removed pump room equipment and conduit  
Check mark Installed four equipment panels
Check mark Wired 11 signal cases
Check mark Replaced 16 tie blocks
Check mark Completed asbestos abatement in two pump rooms
Check mark Installed 1,300 feet of permanent signal cable straps
Check mark Installed 10 signal riser boxes
Check mark Installed signal equipment
February 2 – 5: Next round of work