Weekend Work
Thirty–first Weekend Completed
Check markWhat we accomplished
     January 12 – 15  
 

Check mark Installed seven fiber optic cable supports
Check mark Installed 810 feet of fiber optic cable
Check mark Installed 6,290 feet of permanent strapping for communications and signal cable
Check mark Installed 12,447 feet of cable
Check mark Replaced 40 feet of previously chopped duct banks
Check mark Installed 90 feet of conduit
January 19 – 22: Next round of work