Weekend Work
Thirtieth Weekend Completed
Check markWhat we accomplished
     January 5 – 8   
 

Check mark Performed repairs/adjustments to 10 signal risers
Check mark Installed scaffolding above stair for conduit installation
Check mark Strapped 900 feet of communication cable
Check mark Installed 220 feet of communication cable conduit and 160 feet of fiber optic cable conduit
Check mark Installed additional 280 feet of replacement conduit
Check mark Installed 3,053 feet of signal cable
Check mark Installed 33 support racks
Check mark Installed 528 feet of fiber optic cable
Check mark Temporarily strapped 7,700 feet of fiber optic cable and installed 1,360 permanent straps to secure communication cable
Check mark Installed three signal heads
Check mark Drilled 10 cores
Check mark Dug out concrete trench for fiber optic conduits
January 12 – 15: Next round of work