Weekend Work
Twenty-eighth Weekend Completed
Check markWhat we accomplished
     December 22 – 25  
 

Check mark Installed 475 feet of conduit, including two condulets
Check mark Installed five support racks
Check mark Installed 10 junction boxes
Check mark Installed 300 feet of inner duct
Check mark Pulled 5,790 feet of fiber optic cable
Check mark Pulled 1,600 feet of communications cable
Check mark Poured three concrete signal pads

Next round of work: December 29 – January 1