Weekend Work
Twenty-seventh Weekend Completed
Check markWhat we accomplished
     December 15 –18  
 

Check mark Installed 1,465 feet of conduit, including seven condulets
Check mark Installed six support racks
Check mark Drilled four cores
Check mark Installed 9,460 feet of fiber optic cable
Check mark Poured 300 feet of concrete for new track installation

Next round of work: December 22 – 25