Weekend Work
Twenty-fourth Weekend Completed
Check markWhat we accomplished
     November 24 – 27   
 

Check mark Installed 800 feet of messenger cable
Check mark Chopped out 100 feet of concrete track bed and installed track braces
Check mark Installed 20 feet of antenna cable
Check mark Installed 620 feet of conduit for duct bank replacement
Check mark Chopped out eight openings at Borough Hall
Check mark Installed 1,600 feet of piping
Check mark Drilled three holes for conduit installation
Check mark Installed 1,250 feet of wiring
Check mark Installed 1,155 feet of conduit and 44 brackets

Next round of work: December 1 – 4  