Weekend Work
Eighth Weekend Completed
Check markWhat we accomplished
     August 4 – 7
 

Check mark Repaired 1,106 feet of concrete cracks
Check mark Repaired four square feet of spalled concrete
Check mark Installed 3,850 feet of power cable
Check mark Installed 3,050 feet of signal cable
Check mark Installed 5,940 feet of sound powered telephone cable
Check mark Delivered 3,000 feet of continuous welded rail for future installation