Weekend Work
Twenty-ninth Weekend Completed
Check markWhat we accomplished
     December 29 – January 1  
 

Check mark Installed 210 feet of conduit, including 15 conduit connectors/fittings
Check mark Installed 240 feet of sleeves for previously chopped ducts
Check mark Installed 10 signal junction boxes
Check mark Installed 6,318 feet of fiber optic cable
Check mark Installed 38 straps for signal cables
Check mark Installed 12 support racks, 14 steel straps, and two pull boxes.
Check mark Drilled seven cores
Check mark Repaired 28 patched duct sections

Next round of work: January 5 – 8