Grant Management
The following list presents six recently awarded Federal Transit Administration (FTA) grants. NY-2020-069, NY-2020-074, NY-2020-077 funded projects for LIRR, MNR, NYCT and NY-2020-011-01 (CARES Act) grant and its amendment funded MTA operating assistance. The grant amendments NY-2019-057-01 and NY-2019-058-01 added funding to an existing MTA Bus grant. This is the MTA's final program of projects for the Section 5307 funding obligated in Federal Fiscal Year 2020.
The non-CARES Act grants obligated a total of $ $661,222,414 of Section 5307 funds for NYCT, LIRR, MNR and MTA Bus were executed between July and September, 2020. The public hearings for the proposed program of projects were held by the Metropolitan Transportation Authority, on September 6, 2018 and January 15, 2020. This list is provided to the public as required by 49 USC 5307.
The CARES Act grant in the amount of $4,009,469,417 administered under the Urbanized Area Formula Program (49 USC 5307) and awarded by Federal Transit Administration (FTA) was for MTA operating assistance.
Agency |
PIN |
Description |
Federal Amount $ |
NY-2020-069 |
|||
LIRR |
L8040102 |
LIRR Replacement and Rehabilitation of Bridges |
$40,700,000 |
LIRR |
L8030101 |
LIRR Construction Equipment and Geometry Cars |
$40,000,000 |
MNR |
M8030101 |
MNR 2020 Cyclical Track Program |
$18,805,000 |
MNR |
M8030103 |
MNR 2020 Cyclical Turnouts Mainline and GCT |
$8,353,000 |
MNR |
M7030304 |
MNR Moodna Viaduct Repair |
$9,650,000 |
NYCT |
T8050201 |
NYCT Main Track Replacement Rutgers Tube |
$16,093,830 |
NYCT |
T8050207 |
NYCT Mainline Track Rehab Direct Fixation QBL MW26-8933 |
$52,800,000 |
NYCT |
T8050207 |
NYCT Mainline Track Rehab Direct Fixation 63 St Line MW26-8933 |
$27,200,000 |
NYCT |
T8090401 |
NYCT Rehabilitation of 5 Circuit Breaker Houses Enclosures MW25-2553 |
$12,416,000 |
NYCT |
T8090204 |
NYCT Avenue O substation renewal and CBH 588 Culver Line PW11-2291 |
$38,598,255 |
|
|
Subtotal |
$264,616,085 |
NY-2020-074 |
|||
LIRR |
L8020411 |
ADA Station Renewal Locust Manor |
$15,000,000 |
LIRR |
L8020414 |
ADA Station Renewal St Albans |
$7,000,000 |
MNR |
M8020202 |
ADA Wakefield Station Renewals Harlem Line |
$20,804,729 |
NYCT |
T80413A1 |
ADA 95 Street at 4 Av Line |
$26,432,010 |
NYCT |
T80413A1 |
ADA Avenue H (northbound) at Brighton Line |
$20,000,000 |
NYCT |
T80413A1 |
ADA Huguenot Station SIRTOA |
$27,179,763 |
NYCT |
T8041204 |
Platform Components Metropolitan Av Crosstown Line |
$8,488,003 |
NYCT |
T8041203 |
Station Components New Dorp Station SIRTOA |
$4,040,380 |
NYCT |
T80413A1 |
ADA 95 Street at 4 Av Line |
$26,432,010 |
|
|
Subtotal |
$131,868,675 |
NY-2020-077 |
|||
LIRR |
L8050102 |
Communication Component Replacement |
$1,600,000 |
LIRR |
L8050101 |
Communication Pole Line |
$1,600,000 |
LIRR |
L8070104 |
Third Rail Upgrades |
$8,300,000 |
LIRR |
L8070102 |
Lighting Improvements |
$11,600,000 |
LIRR |
L8020402 |
Station Platform Components Repairs and Replacements |
$19,200,000 |
LIRR |
L8050205 |
Signal Normal Replacement Program |
$33,400,000 |
LIRR |
L8050201 |
Babylon Interlocking Renewal and New Sidings |
$52,600,000 |
LIRR |
T8090402 |
Negative Cables 36 St - Pacific St 4 Av Line |
$42,461,190 |
LIRR |
T8060504 |
Deep Wells Rehab Phase 2 Nostrand Line |
$17,518,457 |
LIRR |
T8060504 |
Pump Rooms Rehabilitation 6 Locations |
$61,600,000 |
LIRR |
T8060504 |
Fan Plant Component Repairs 8Av Line (Fiber Only) |
$6,560,001 |
|
|
Subtotal |
$256,439,648 |
NY-2019-057-01 MTA Bus Section 5307 – 2017/2018 |
|||
MTA Bus |
U7030213 |
Chassis Wash - College point |
$1,724,406 |
MTA Bus |
U70302015 |
MTA Bus - Project Administration |
$2,100,000 |
MTA Bus |
U7030216 |
MTA Bus - Engineering Design Mgmt Services |
$2,700,000 |
|
|
Subtotal |
$6,524,406 |
|
|||
NY-2019-058-01 MTA Bus Section 5307 – 2018 |
|||
MTA Bus |
U6030222 |
MTA Bus - Construction Mgmt Services - Multi-Year |
$1,773,600 |
|
|
Subtotal |
$1,773,600 |
|
|
||
NY-2020-011-01 |
|||
MTA |
Not applicable |
MTA Section 5307 CARES ACT Operating |
$4,009,469,417 |
|
|
Subtotal |
$4,009,469,417 |
|
|
Total |
$4,670,691,831 |