Skip to main content
Go to MTA homepage
 

Brief Descriptions of Work to be Advertised

** Partially Funded by Federal grant(s)


New York City Transit
Brief Description of Work
DEC 2019

P36692
ROOF AND ENCLOSURE: CONCOURSE E. 144TH ST - WRAP-UP [SBMP]
$500 - $1M

This Small Business Mentoring Project is to wrap up the roof and enclosure rehabilitation of the Concourse - East 144th Street Substation on the Jerome Line in the Bronx. Work will include:

Duration of Contract 12 Months


A37136
ADA ENHANCEMENTS: QUEENSBORO PLAZA / FLUSHING
$25M - $50M

This Design/Build project is to provide full ADA accessibility at the Queensboro Plaza Station on the Flushing Line. Work will include:

Duration of Contract Months


A37691
STATION CIRCULATION ENHANCEMENTS: MAIN STREET / FLUSHING
$25M - $50M

This Design/Build project is to increase circulation capacity at the Main Street Station on the Flushing Line. Work will include:

Duration of Contract Months


New York City Transit
Brief Description of Work
JAN 2020

B32804
PAINT BOOTH: YUKON DEPOT [SBMP TIER2]
$1M - $5M

This Small Business Mentoring Project is to provide all labor, tools, equipment necessary for installing, testing and putting into operation a new paint booth at the Yukon Bus Depot in Staten Island. Work will include:

Duration of Contract 18 Months


C34857
SANDY REPAIRS: ROCKAWAY LINE WRAP-UP**
$25M - $50M

This project is to provide repairs along the Rockaway Line in Queens, to address damage resulting from Superstorm Sandy. Work will include:

Duration of Contract 36 Months


C34874/C52091
LIVINGSTON PLZ ELEC AND MECH SYS IMPROVEMENTS, PH B AND EMERGENCY GENERATOR
$25M - $50M

This project is to upgrade the electrical and mechanical infrastructure systems and provide an additional redundant emergency generator system within the 130 Livingston Plaza Building in Brooklyn. Work will include:

Duration of Contract 32 Months


C40205
WINDOW REPLACEMENT FLATBUSH & ULMER PARK DEPOTS
$5M - $10M

This project is to provide architectural, civil, mechanical and electrical work for window replacement and associated brick repairs at Flatbush Bus Depot & Ulmer Park Bus Depot in Brooklyn. Work will include:

Duration of Contract 18 Months


C34919
OVERCOATING: 17 BRIDGES & EAST 180 STREET FLYOVER / DYRE AV
$25M - $50M

This Design/Build project is to provide overcoat painting and steel repairs on 17 Bridges and the Flyover at E. 180th Street on the Dyre Avenue Line in the Bronx. Work will include:

Duration of Contract 24 Months


New York City Transit
Brief Description of Work
FEB 2020

E34028
REPLACE 8 TRACTION ELEVATORS / VARIOUS**
$25M - $50M

This project is to replace eight traction elevators at four stations: one at 63rd St (Lex Ave), two at 63rd St (Roosevelt Island), two at Court St.,(BMT-Bklyn), and three at Clark St (IRT-Bklyn). Work will include:

Duration of Contract 36 Months


P36712/P36704
SANDY MITIGATION: MONTAGUE-FURMAN SUBSTATION / BWY**
$1M - $5M

This project is to provide resiliency work at Montague Furman Substation in the Borough of Brooklyn. Work will include:

Duration of Contract 18 Months


New York City Transit
Brief Description of Work
MAR 2020

A37671
SANDY MITIGATION: 138 ST - GR CONCOURSE/JER (VENT BATTERY A)**
$1M - $5M

This project is to rehabilitate the southern vents at 138th St-Grand Concourse Station in the Bronx and provide flood resiliency measures. Work will include:

Duration of Contract Months


C34924
SANDY MITIGATION: STEINWAY PORTAL(9 STNS BK/Q INITIATIVE)**
$10M - $25M

This project is to construct flood mitigation measures to protect the Steinway tunnel portal on the Flushing Line in the borough of Queens. Work will include:

Duration of Contract 36 Months


A35304/A37135
ADA AND STATION RENEWAL WOODHAVEN BOULEVARD / JAMAICA
OVER $50M

This Design/Build project is to renew and provide accessibility upgrade at Woodhaven Boulevard Station on the Jamaica Line in the borough of Queens. Work will include:

Duration of Contract 48 Months


A35305 / 06 /07
STATION RENEWAL, 3 STATIONS / JAMAICA
OVER $50M

This Design/Build project is to renew stations at Cypress Hills, 85 street- Forest Parkway and 75 Street-Elderts Lane on the Jamaica Line in the boroughs of Brooklyn and Queens. Work will include:

Duration of Contract Months


A37121
ADA: COURT SQUARE / CROSSTOWN (ELEVATOR PHASE)
$10M - $25M

This Design/Build project is to provide full ADA accessibility at the Court Square Station in the Borough of Queen. Work will include:

Duration of Contract Months


A37131
ADA: 149 STREET - GRAND CONCOURSE COMPLEX
OVER $50M

This Design/Build project is to provide vertical accessibility at the 149th Street grand Concourse Station Complex, Grand Concourse Line, on the Jerome Avenue Line (No. 4 Line) and White Plains Road Line (Nos. 2 and 5 Lines) in the Borough of the Bronx.

Duration of Contract Months


C33941
ROOF REPLACEMENT: TIFFANY CENTRAL WAREHOUSE
$10M - $25M

This Design/Build project is to replace the existing single ply EPDM membrane roofing system at the Tiffany Street Store Room in the borough of the Bronx. Work will include:

Duration of Contract 24 Months


A46026/27/28/29/31/C48729
STATION RENEWAL WORK ON THE FLUSHING (7) LINE INCLUDING TRACK AND STRUCTURE SUPPORTING STEEL REPAIR/REPLACEMENT AT 61 ST-WOODSIDE-FLS
OVER $50M

This Design/Build project is to provide station renewal work at specified NYCT elevated and below ground stations on the Flushing (7) line. Work will include:

Duration of Contract Months


New York City Transit
Brief Description of Work
APR 2020

A36164
ADA: 68 ST-HUNTER COLLEGE / LEXINGTON**
OVER $50M

This Design/Build project is to provide full ADA accessibility at the 68th Street-Hunter College Station on the IRT Lexington Avenue Line located in the Borough of Manhattan. Work will include:

Duration of Contract 33 Months


P36708
NEW SUBSTATION: CANAL STREET / 8TH AVENUE
$25M - $50M

This Design/Build project is to construct a new substation serving the IND, 8th Avenue Line around Canal Street and 8th Avenue in the borough of Manhattan in order to provide traction power for reliable train operations on the 8th Avenue Line.

Duration of Contract 39 Months


New York City Transit
Brief Description of Work
JUN 2020

A37289
STAIRS: 14TH ST-6TH AVE (S2/M4,S5/M11,S7/M13) [SBMP TIER2]
$1M - $5M

Duration of Contract Months


A37139
ADA: 95TH ST / 4AV
$25M - $50M

Duration of Contract 33 Months


New York City Transit
Brief Description of Work
AUG 2020

A37344
STATION PAINTING AT COMP LOCATION: PELHAM BAY PARK/PELHAM
$1M - $5M

Duration of Contract Months


C48705
LSCRP: DOWNTOWN MANHATTAN (BWY, 8AV)
$25M - $50M

Duration of Contract Months


New York City Transit
Brief Description of Work
SEP 2020

A37694
GRAND CENTRAL: WIDENING STAIRS PL-8 /PL-9 / FLUSHING
$1M - $5M

Duration of Contract 14 Months


A37695
GRAND CENTRAL: WIDENING STAIRS U2/U6 / LEXINGTON
$5M - $10M

Duration of Contract 14 Months


C40901
FIRE ALARM SYSTEMS: 2 DOS LOCATIONS [SBMP TIER2]
$1M - $5M

Duration of Contract Months


C40902
FIRE ALARM SYSTEMS: 2 DOS LOCATIONS [SBMP TIER2]
$1M - $5M

Duration of Contract Months


New York City Transit
Brief Description of Work
OCT 2020

PW01-3825
SANDY MITIGATION: HARDENING OF SUBSTATIONS - 4 LOCS**
$25M - $50M

Duration of Contract Months


New York City Transit
Brief Description of Work
NOV 2020

D61445/D61446/PW01-3825
SANDY MITIGATION: TUDOR SUBSTATION, WEST BDWY/MURRAY SUBSTN FLOOD PROTECTION, HARDENING OF SUBSTATIONS 12 LOCS**
$25M - $50M

Duration of Contract 24 Months


PW01-3825
SANDY MITIGATION: HARDENING OF SUBSTATIONS - 11 LOCS**
$25M - $50M

Duration of Contract 24 Months


Long Island Rail Road
Brief Description of Work
DEC 2019

L11409
WRECK LEAD BRIDGE REHABILITATION
$1M - $5M

Rehabilitation of the Wreck Lead Bridge (over Reynolds Channel) including safety repairs and priority mechanical items that address bridge seating issues.

Duration of Contract 12 Months


Long Island Rail Road
Brief Description of Work
JAN 2020

E04979
LONG ISLAND CITY YARD RESILIENCY**
$10M - $25M

Long Island City Yard Restoration/Resiliency: Perimeter Flood Wall, Pumping Stations and Restoration of Tracks 11 and 12

Duration of Contract 24 Months


Long Island Rail Road
Brief Description of Work
JUN 2020

E03405
WEST SIDE YD/EAST RVR TNL**
$25M - $50M

Duration of Contract 24 Months


E03408
ERT QUEENS PORTALS FLOOD MITIGATION**
$25M - $50M

Duration of Contract 24 Months


Long Island Rail Road
Brief Description of Work
JUL 2020

L11989
CENTRALIZED TAIN CONTROL - UWB TRAIN POSITIONING
$1M - $5M

Duration of Contract 6 Months


L12164
BABYLON TO PATCHOGUE**
$100K - $500K

Duration of Contract 4 Months


Long Island Rail Road
Brief Description of Work
AUG 2020

L11933
SUB REP PKG 2
$10M - $25M

Duration of Contract 29 Months


Long Island Rail Road
Brief Description of Work
OCT 2020

L11143
SUBSTATION COMPONENTS
$1M - $5M

Duration of Contract 18 Months


L12052
HALL AND BABYLON SIGNAL POWER MOTOR GENERATOR REPLACEMENT
$5M - $9M

Duration of Contract 24 Months


Metro-North Railroad
Brief Description of Work
DEC 2019

M10717
HARLEM LINE STATION IMPROVEMENTS**
$10M - $25M

This project will install 3 new elevators, (two at Hartsdale and one at Scarsdale (inbound) including walkway extensions from the overpass to the new elevators and the accompanying elevator machine rooms. Additional work at Hartsdale station includes a Coned electrical service upgrade. Additional work at Scarsdale Station includes jacking of the pedestrian overpass to provide Plate E clearance, demolish the existing communication hut, and building a new communication room on the west side of the inbound platform north of the new elevator for the communications equipment.

Duration of Contract 20 Months


M11363
(CONSTRUCTION A+B) MOODNA/WOODBURY VIADUCT**
$5M - $10M

This contract will be responsible for the timber ties replacement on the Moodna Viaduct located just east (south) of the Cornwall-Salisbury Mills Station in Salisbury, NY. The viaduct is a riveted built-up two girders system that is 3,200 feet long and 195 feet tall at its highest point. The viaduct is a single track with walkways on both sides.

Duration of Contract 24 Months


Metro-North Railroad
Brief Description of Work
JAN 2020

M11183/M11184/M11723
CONSTRUCTION/ENVIRONMENTAL
$10M - $25M

The purpose of this project is to construct a unified trash handling facility to be employed jointly by Metro-North and Long Island Railroads, in support of the future LIRR ESA Concourse. This trash handling facility will be constructed on the existing platform adjacent to track 115 located on the Lower Level of Grand Central Terminal, next to the proposed LIRR Concourse service corridor, where Metro-North will load trash for both railroads onto railcars for transport to BN Yard and disposal. This Track 115 Trash Transfer Facility provides safe, efficient rail service to the trash facility. Trackwork and related systems improvements, which reinstate a connection of "Ladder N" to Track 115 to facilitate train movements serving the facility are incorporated into the project.

Duration of Contract 24 Months


Metro-North Railroad
Brief Description of Work
FEB 2020

M10469
PBX SOFTWARE/HARDWARE
$1M - $5M

This contract will provide UPS (Uninterruptible Power Supply) and power distribution hardware associated with PBX (Private Branch Exchange) equipment at five (5) Metro-North Railroad locations (see below). Interface UPS to centralized reporting system. Provide software upgrade for PBX Signaling Server. Provide expansion hardware for additional users at the PBX to existing system. Locations: South East, North White Plains, Mott Haven, Croton Harmon and Poughkeepsie.

Duration of Contract 16 Months


Metro-North Railroad
Brief Description of Work
MAR 2020

M11505
MOTOR CARS WITH TOOL CIRCUITS
$500K-$1M

This contract will provide for the purchase of four (4) Motor Cars with Tool Circuits for Metro-North Railroad's Maintenance of Way machine shop. Specifications and modifications include additional tool storage, perimeter lighting and tool circuits with retractable reels.

Duration of Contract 9 Months


M11507
RAIL LIFTER
$200K-$500K

This contract will provide for the purchase of two (2) Rail Lifters for Metro-North Railroad's Maintenance of Way machine shop. Specifications and modifications include third rail clearance, LED Lighting and perimeter lighting.

Duration of Contract 8 Months


M11509
BALLAST REGULATOR
$1M-$5M

This contract will provide for the purchase of seven (7) Ballast Regulators for Metro-North Railroad's Maintenance of Way machine shop. Specifications and modifications include perimeter lighting, dust control system, third rail clearance, LED lighting and reflective tape.

Duration of Contract 13 Months


M11510
SPEED SWING
$800K-$1.5M

This contract will provide for the purchase of two (2) Speed Swings for Metro-North Railroad's Maintenance of Way machine shop. Specifications and modifications include third rail clearance, high rail equipment, train coupler and air system and reflective tape.

Duration of Contract 13 Months


M11511
ALL TERRAIN HI-REACH FORKLIFT
$100K-$500K

This contract will provide for the purchase of one (1) All Terrain Hi-Reach Forklift for Metro-North Railroad's Maintenance of Way machine shop. Specifications and modifications include enclosed cab with HVAC equipment.

Duration of Contract 6 Months


M11513
ROUGH TERRAIN ARTICULATING BOOM LIFT
$100K-$300K

This contract will provide for the purchase of one (1) Rough Terrain Articulating Boom Lift for Metro-North Railroad's Maintenance of Way machine shop.

Duration of Contract 5 Months


M11514
HYDRAULIC METAL SHEAR (NWP SHOP)
$50K-$100K

This contract will provide for the purchase of one (1) Hydraulic Metal Shear for Metro-North Railroad's Maintenance of Way machine shop.

Duration of Contract 5 Months


M11515
HYDRAULIC METAL BRAKE (NWP SHOP)
$50K-$100K

This contract will provide for the purchase of one (1) Hydraulic Metal Brake for Metro-North Railroad's Maintenance of Way machine shop.

Duration of Contract 5 Months


M11517
RAIL HEATER
$500K-$1M

This contract will provide for the purchase of one (1) Rail Heater for Metro-North Railroad's Maintenance of Way machine shop. Specifications and modifications include enclosed cab with HVAC equipment, perimeter lighting and reflective tape.

Duration of Contract 10 Months


M11518
WHEEL LOADER
$100K-$500K

This contract will provide for the purchase of one (1) Wheel Loader for Metro-North Railroad's Maintenance of Way machine shop. Specifications and modifications include 4 in one bucket, side dump, hydraulic quick connects for bucket change out, forks and snow pusher.

Duration of Contract 6 Months


Metro-North Railroad
Brief Description of Work
MAY 2020

M10991
CONSTRUCTION OF NODE HOUSE ROOFS
$500K - $1M

This contract is for the survey of 36 locations for a 10‿x 20‿ communication bungalow and furnishes, deliver and install new roofing system as needed. Metro North Railroad has 36 locations spread out on all three lines (Harlem, Hudson and New Haven) that have communication bungalows that require an assessment for the replacement of their roofs. The work includes survey and assessment of the current communication houses roof condition (includes water proofing membrane). Based on the determination of the findings the existing roofs must be replaced, as needed, with new roofing systems. The work must be performed in a matter that is non disruptive to railroad operations and free of damage to equipment within the space.

Duration of Contract 16 Months


Bridges and Tunnels
Brief Description of Work
FEB 2020

[20-24 Project] MP-09
DESIGN-BUILD: REHABILITATION OF THE TOWER ELEVATORS AT THE MARINE PARKWAY BRIDGE
$10M - $25M

Under this Design-Build contract, the design-builder will perform rehabilitation and electrical upgrades to the tower elevators at the Marine Parkway Bridge.

Duration of Contract 30 Months


[20-24 Project] RK-82
DESIGN-BUILD: CONSTRUCTION OF A STORAGE FACILITY AT THE ROBERT F. KENNEDY BRIDGE
$10M - $25M

Under this Design-Build contract, the design-builder will design and construct a storage facility for spare parts and emergency response equipment at the Robert F. Kennedy Bridge.

Duration of Contract 30 Months


Bridges and Tunnels
Brief Description of Work
MAR 2020

[20-24 Project] VN-X1
DESIGN-BUILD: SAFETY FENCING AT THE VERRAZZANO-NARROWS BRIDGE
$25M - $50M

Under this Design-Build contract, the design-builder will design and construct safety fencing at the Verrazzano-Narrows Bridge.

Duration of Contract 36 Months


Bridges and Tunnels
Brief Description of Work
JUN 2020

[20-24 Project] RKPT
CONSTRUCTION: STRUCTURAL PAINTING AT THE ROBERT F. KENNEDY BRIDGE
$10M - $25M

Under this Construction contract, the contractor will perform blast cleaning and full overcoat painting of a portion of the Robert F. Kennedy Bridge steel.

Duration of Contract 24 Months


MTA Bus
Brief Description of Work
DEC 2019

C-40261
HVAC- SPRING CREEK DEPOT
$1M - $5M

This project will replace the HV and A/C units and associated equipment at the Spring Creek Depot. Procurement will be done on behalf of MTA Bus by MTA New York City Transit.

Duration of Contract 22 Months


C-40274
DEPOT REHAB: COLLEGE POINT**
$5M - $10M

This project is rehab/renovation of various components at the College Point Depot. Procurement will be done on behalf of MTA Bus by MTA New York City Transit.

Duration of Contract 16 Months


C-40275
STOREROOM EXPANSION - LAGUARDIA**
$5M - $10M

This project is for the reconfiguration/upgrade of the LaGuardia Depot storeroom. Procurement will be done on behalf of MTA Bus by MTA New York City Transit.

Duration of Contract 18 Months


C-40276
WINDOW REPLACEMENT - JFK**
$1M - $5M

This project will replace overaged/dilapidated windows at the JFK Depot. Procurement will be done on behalf of MTA Bus by MTA New York City Transit.

Duration of Contract 12 Months

** Partially Funded by Federal grant(s)

  • Google Translate