  • Project Schedule
    Environmental Assessment

    • Public Information Centers: January 29 & 30, 2015
    • Draft Environmental Assessment: May 2015
    • Public Comment Period: June 2015
    • Environmental Determination: July 2015


Construction*

  • Preliminary Design (30%): July 2015
  • Procurement and Design-Build Contract Award: 1st Qtr 2016
  • Construction Complete: 4th Qtr 2018

*Tentative construction dates assuming that thereis a determination of no environmental impacts.