Schedule

  • $138M Committed to Expedite Double Track
    May 2012

  • Phase I - Awarded Design/Environmental Contract
    July 2012

  • Phase I - Design/Build Award and Construction
    December 2013 – Start
    September 2016 – Complete laying of first section of track
    2018 – Complete signaling and other track elements

  • Phase II - Preliminary Design
    January 2015 - September 2015

  • Phase II - Design/Build Award and Construction
    April 2016 - December 2018