Schedule

  • $138M Committed to Expedite Double Track
    May 2012

  • Phase I - Awarded Design/Environmental Contract
    July 2012

  • Phase I - Design/Build Award and Construction
    November 2013 - September 2016

  • Phase II - Preliminary Design
    January 2015 - September 2015

  • Phase II - Design/Build Award and Construction
    April 2016 - December 2018