Project Phasing

PHASE 1 Feb 2015-
May 2015
Colonial Road
Closed
(March 30 2015
to March 2016)
  • Set up staging area
  • Removal of vegetation
  • Installation of temporary fencing (Feb 2015)
  • Utility Relocations
  • Begin installation of retaining walls and bridge foundation
Daytime/Weekday Work
*except for daytime work on Saturday, May 9
PHASE 2 June 2015-
Sep 2015
Colonial Road
Closed
  • Continue installation of retaining walls and bridge foundation
  • Bridge demolition (June 2015)
  • Installation of drainage
Daytime/Weekday Work*
*except for continuous day and overnight work during one weekend on June 19-22 for bridge demolition
PHASE 3 Sep 2015-
Oct 2015
Colonial Road
Closed
  • Installation of precast bridge elements (Sep-Oct 2015)
  • Installation of drainage

Daytime/Weekday Work*
*except for continuous day and overnight work during two weekends in Sep/Oct for bridge installation

PHASE 4 Oct 2015-
June 2016
Colonial Road
open to the public
(March 2016)
  • Reinstallation of overhead wires
  • Construction of new roadway
  • Installation of pocket track
  • Installation of drainage
Daytime/Weekday Work
PHASE 5 June 2016-
Oct 2017
 
  • Design and material
  • procurement for pocket track extension
  • Installation of landscaping
Minimal on-site activity
PHASE 6 Nov 2017-
Dec 2018
 
  • Installation of switch and signals
Daytime/Weekday Work*
*except for continuous day andovernight work during three weekends (to be determined)