Passenger Stations   Budget   Schedule  


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Fare Collection
New Fare Payment System, Phase 2 Construction $518,597,000 $518,597,000 0% Nov 2017 Nov 2017 2023
Procurement of Low Turnstile Automated Fare Control Construction $11,640,000 $11,640,000 0% 2016 May 2017 2020
Replace Automated Fare Collection (AFC) Components Construction $13,861,520 $13,861,520 0% Dec 2017 2020
Fare Control Area Improvements  Superseded $0 $0 0%
Station Escalators / Elevators
Replace 11 Hydraulic Elevators at Various Locations   Design    $51,143,758 $51,143,758 0% 2019 2019
Replace 12 Traction Elevators on the Broadway/7th Avenue Line Construction $98,259,326 $98,259,326 0% 2017 Apr 2018 2021
Replace 8 Traction Elevators at Various Locations   Design    $61,727,178 $61,727,178 0% 2017 2019
Replace 6 Traction Elevators on the 8th Avenue Line   Design    $50,581,616 $50,581,616 0% 2018 2018
Replace 2 Hydraulic Elevators at Borough Hall on the Clark Street Line   Design    $16,511,053 $16,312,857 (1%) 2016 2019
Replace 2 Escalators and 2 stairs at Grand Central Station   Design    $23,290,551 $23,290,551 0% 2017 2018
Replace 7 Escalators at Various Locations in the Bronx and Manhattan   Design    $42,230,558 $39,602,524 (6%) 2019 2019
Replace 2 Escalators at Pelham Parkway on the White Plains Road Line   Design    $15,289,076 $15,289,076 0% 2018 2019
Replace 6 Escalators at Various Locations   Design    $32,712,141 $29,989,281 (8%) 2018 2019 2022
Jay Street Escalator Realignment   Design    $15,000,000 $15,000,000 0% 2017 2018 2019
Replace 2 Hydraulic Elevators at Franklin Avenue on the Franklin Avenue Shuttle   Design    $15,144,200 $14,561,286 (4%) 2019 2019
Replace 3 Escalators at Main Street on the Flushing Line   Design    $20,313,388 $20,313,388 0% 2019 2019
Replace 5 Escalators at Various Locations in Brooklyn and Manhattan   Design    $26,254,022 $26,254,022 0% 2019 2019
Replace Hydraulic Elevator at Grand Central on the Flushing Line   Design    $10,585,527 $10,277,300 (3%) 2019 2019
Station Work
Water Remediation - Renewal at Borough Hall Station on the Lexington Avenue Line   Design    $43,410,760 $43,410,760 0% 2017 2019 2020
Renewal of 138 St - Grand Concourse Station on the Jerome Line   Design    $29,089,079 $29,291,590 1% 2016 2018
Renewal of Astoria-Ditmars Boulevard Station on the Astoria Line Construction $23,738,512 $23,738,512 0% 2016 Dec 2017 2019
Renewal of Astoria Boulevard Station on the Astoria Line Construction $62,993,020 $52,721,060 (16%) 2017 Jun 2018 2020
Renewal of 30 Avenue Station on the Astoria Line - Design Only   Complete   $1,184,828 $1,184,828 0% 2016 Sep 2014 Nov 2015
Renewal of Broadway Station on the Astoria Line - Design Only   Complete   $1,003,476 $1,003,476 0% 2016 Sep 2014 Nov 2015
Renewal of 36 Avenue Station on the Astoria Line - Design Only   Complete   $1,110,660 $1,110,660 0% 2016 Sep 2014 Nov 2015
Renewal of 39 Avenue Station on the Astoria Line - Design Only   Complete   $1,031,778 $629,421 (39%) 2016 Sep 2014 Nov 2015
Renewal of Mets-Willets Point Station on the Flushing Line   Design    $50,000,000 $50,000,000 0% 2018 2020
Renewal of 111 Street Station on the Flushing Line   Design    $35,000,000 $35,000,000 0% 2018 2019
Renewal of 103 Street-Station Corona Plaza on the Flushing Line   Design    $25,000,000 $25,000,000 0% 2018 2019
Renewal of 82 Street Station-Jackson Heights on the Flushing Line   Design    $24,298,450 $24,298,450 0% 2018 2019
Renewal of Woodhaven Boulevard Station on the Jamaica Line   Design    $45,000,000 $45,000,000 0% 2017 2019
Renewal of 85 Street-Forest Parkway on the Jamaica Line   Design    $25,000,000 $25,000,000 0% 2017 2019
Renewal of 75 Street-Elderts Lane on the Jamaica Line   Design    $25,000,000 $25,000,000 0% 2017 2019
Renewal of Cypress Hills Station on the Jamaica Line   Design    $25,000,000 $25,000,000 0% 2017 2019
Renewal of 69 Street Station on the Flushing Line   Design    $25,000,000 $25,000,000 0% 2019 2019
Renewal of 61 Street Station-Woodside on the Flushing Line   Design    $50,000,000 $50,000,000 0% 2019
Renewal of 52 Street Station on the Flushing Line   Design    $35,000,000 $35,000,000 0% 2019 2019
Renewal of 3 Avenue-138 Street Station on the Pelham Line - Design Only  Superseded $0 $0 0% 2019
Ventilator Repairs at 2 Locations in the Bronx Construction $7,741,058 $6,958,942 (10%) 2016 Oct 2017 2019
Component Repairs at 2 Stations on the 4th Avenue Line   Complete   $11,370,749 $11,370,749 0% 2018 Feb 2017 Apr 2018
Platform Component Repairs at Kingston-Throop Avenue Station on the Fulton Line - Design Only   Complete   $270,725 $270,725 0% 2016
Platform Component Repairs at 2 Locations on the Jerome Line   Design    $19,875,223 $20,260,371 2% 2016 2019
Platform Component Repairs at Pelham Parkway on the Dyre Line - Design Only   Complete   $41,816 $41,816 0% 2016 Nov 2015
Replacement of Street Stairs at 2 Locations on the Broadway-7th Avenue Line (SBMP) - Design Only   Complete   $131,152 $134,252 2% Oct 2015 Oct 2015 Apr 2017
Repair of Subway Interior Stairs at 9 Locations on Various Lines  Superseded $0 $0 0% 2015
Repair of Subway Street Stairs at 2 Locations on Various Lines   Design    $2,996,561 $2,996,561 0% 2016 2018
Station Lighting at 5 Locations on Various Lines (SBMP)   Design    $5,360,654 $5,247,640 (2%) 2016 2019
Ventilator Repairs at Various Locations   Planning  $8,054,122 $8,054,122 0% 2017 2018 2020
Platform Component Repairs at 167 Street on the Grand Concourse Line - Design Only   Complete   $270,772 $270,772 0% 2017 Nov 2015
Repair of Platform Components at Bedford-Nostrand on the Crosstown Line Construction $13,041,776 $9,539,395 (27%) 2017 Aug 2018 2019
Repair of Platform Components at Longwood Avenue on the Pelham Line   Design    $9,909,596 $9,532,266 (4%) 2017 2018
Repair of Platform Components at 2 Locations on the Lenox Line   Design    $11,226,640 $10,715,040 (5%) 2017 2018
Repair of Platform Components at 2 Locations on the Flushing Line   Planning  $11,890,572 $11,890,572 0% 2017 2020
Repair of Elevated Interior Stairs at Junction Boulevard on the Flushing Line (SBMP)   Design    $1,442,153 $1,442,153 0% 2016 2019
Repair of Interior Stair at 14 St-Union Square on the Lexington Avenue Line (SBMP)   Design    $998,868 $998,868 0% 2019 2019 2020
Repair of Elevated Street Stairs at 2 Locations on the White Plains Road Line (SBMP) Construction $1,157,009 $993,906 (14%) 2016 Jul 2018 2019
Repair of Subway Street Stairs at 4 Locations on Various Lines (SBMP) - Design Only   Complete   $2,853,852 $1,316,227 (54%) Sep 2016 Sep 2016 Mar 2018
Repair of Mezzanine Columns at Atlantic Avenue Station on the Canarsie Line (SBMP)   Planning  $5,655,943 $5,655,943 0% 2016 2019
Repair of Mezzanine Ceiling Finishes at 2 Locations on the Archer and Flushing Lines (SBMP)   Design    $4,572,698 $4,572,698 0% 2016 2019
Repair of Platform Components at 4 Locations on the Queens Boulevard and Archer Lines   Design    $34,619,833 $34,619,833 0% 2015 2019
Station Lighting at 4 Locations on Various Lines (SBMP) Construction $1,162,042 $2,082,519 79% 2016 Jul 2018 2019
Ventilator Repairs at Various Locations   Planning  $8,394,255 $8,394,255 0% 2018 2019
Repair Platform Components at 2 Locations on the Nassau Loop - Design Only   Planning  $1,147,091 $1,147,091 0% 2018
Repair of Platform Components at 6 Locations on the Canarsie Line   Design    $25,979,061 $27,227,222 5% 2017 2018 2021
Repair of Platform Components at 3 Locations on the Eastern Parkway and Clark Street Lines   Design    $14,907,994 $14,907,994 0% 2017 2019
Reserve: 2017 Station Painting at Components Locations   Planning  $7,200,000 $7,200,000 0% 2017
Repair of Elevated Interior Stairs at Atlantic Avenue on the Canarsie Line (SBMP)  Superseded $0 $0 0% 2017
Repair of Elevated Street Stairs at Atlantic Avenue on the Canarsie Line (SBMP)   Design    $819,833 $819,833 0% 2017
Repair of Street Stairs at 9 Locations (SBMP) - Design Only   Design    $7,469,592 $460,992 (94%) Feb 2017 Feb 2017 2020
Repair Mezzanine Components at Nevins Street on the Eastern Parkway Line (SBMP)   Design    $6,537,669 $6,537,669 0% 2017 2019
Repair Mezzanine Wall Finishes at Bowery on the Nassau Loop (SBMP) Construction $1,107,348 $1,195,630 8% 2017 Jul 2018 2019
Repair of Platform Components at 2 Locs on the Queens Boulevard Line - Design Only   Design    $1,143,272 $1,143,272 0% 2017 May 2018 2019
Repair Platform Edges at 2 Locations on the Queens Boulevard Line - Design Only   Design    $1,901,841 $1,901,841 0% 2019 May 2018 2019
Station Lighting at 7 Locations on Various Lines (SBMP)   Design    $2,913,410 $2,913,410 0% 2017 2019
Platform Component Repairs at 3 Locations on the Nostrand Avenue Line   Design    $25,924,634 $25,629,355 (1%) 2017 2018
Ventilator Repairs at Various Locations   Planning  $8,722,428 $8,722,428 0% 2019 2019
Repair Platform Components at 2 Locations on the Brighton Line - Design Only   Planning  $1,250,572 $1,250,572 0% 2018
Repair Platform Components at 8 Locations on the 8 Avenue Line - Design Only   Planning  $3,156,008 $3,156,008 0% 2018
Repair Platform Components at 10 Locations on the Broadway-7 Avenue Line   Design    $50,108,160 $50,108,160 0% 2018 2019
Reserve: 2018 Station Painting at Components Locations   Planning  $4,500,000 $4,500,000 0% 2018
Repair Interior Stairs at Ocean Parkway on the Brighton Line (SBMP)  Superseded $0 $0 0% 2018
Repair Interior Stairs at 5 Locations on the 8 Avenue and Broadway-7 Avenue Line (SBMP)   Design    $12,848,614 $12,848,614 0% 2018 2019
Repair Elevated Street Stairs at 2 Locations on the Brighton Line (SBMP) - Design Only   Complete   $2,149,054 $152,384 (93%) 2018 Aug 2017 May 2018
Repair Street Stairs at 4 Locations on the 8 Avenue and Broadway-7 Avenue Line (SBMP) - Design Only   Complete   $325,843 $525,000 61% 2018 Apr 2017 Mar 2018
Repair Mezzanine Components at 3 Locations on the 8 Avenue and Lexington Avenue Lines (SBMP)   Planning  $1,957,230 $1,957,230 0% 2018 2019
Station Lighting at 9 Locations on Various Lines (SBMP)   Design    $7,664,834 $7,664,834 0% 2018 2019
Ventilator Repairs at Various Locations   Planning  $9,722,428 $9,722,428 0% 2019 2019
Repair Platform Components at 4 Locations on the 6 Avenue and East 63 Street Lines - Design Only   Design    $1,385,737 $1,385,737 0% 2019 Jun 2018 2019
Repair Platform Components at 6 Locations on the Lexington Avenue Line - Design Only   Planning  $1,893,184 $1,893,184 0% 2019
Repair Platform Edges at Freeman Street on the White Plains Road Line   Design    $1,484,310 $1,484,310 0% 2019 2018
Reserve: 2019 Station Painting at Components Locations   Planning  $3,000,000 $3,000,000 0% 2019
Repair Interior Stairs at 4 Avenue-9 Street on the 6 Avenue Line (SBMP) Construction $548,650 $729,971 33% 2019 Jul 2018 2019
Repair Interior Stairs at 5 Locations on the 8 Avenue (SBMP)   Design    $7,693,426 $7,693,426 0% 2019 2019
Repair Elevated Street Stairs at 3 Locations on the White Plains Road Line (SBMP) Construction $2,600,783 $2,439,605 (6%) 2019 Jul 2018 2019
Repair Street Stairs at 50 Street on the 8 Avenue Line (SBMP) Construction $1,789,765 $1,582,775 (12%) 2019 Jul 2018 2019
Repair Mezzanine Components at 149 St-Grand Concourse on the White Plains Road Line (SBMP)   Planning  $4,208,013 $4,208,013 0% 2019 2019
Repair Mezzanine Floors at 23 Street on the 8 Avenue Line (SBMP) - Design Only   Design    $170,718 $170,718 0% 2019 Sep 2017
Station Lighting at 3 Locations on Various Lines (SBMP)   Design    $5,538,280 $5,538,280 0% 2019 2019
Repair Station Components at 3 Locations on the 8 Avenue Line - Design Only   Planning  $750,000 $750,000 0% 2018
Repair Interior Stairs at 59 Street on the 4 Avenue Line   Planning  $1,701,271 $1,701,271 0% 2018
Repair Street Stairs at 59 Street on the 4 Avenue Line  Superseded $0 $0 0% 2018
Enhanced Station Initiative   Complete   $24,614,261 $24,299,555 (1%) 2016
Repair of Subway Interior Stairs at Canal Street on the Broadway Line (SBMP) Construction $3,679,322 $1,461,959 (60%) 2017 Mar 2018 2018
Enhanced Station Initiative: Package 4 - 34th St-Penn Station on the Broadway-7th Avenue Line Construction $30,025,798 $30,165,217 0% Feb 2018 2019
Enhanced Station Initiative: Package 2 - Broadway on the Astoria Line Construction $49,120,442 $49,120,442 0% Apr 2017 Apr 2017 2019 2019
Enhanced Station Initiative: Package 2 - 30 Avenue on the Astoria Line Construction $65,474,784 $65,474,784 0% Apr 2017 Apr 2017 2019 2019
Enhanced Station Initiative: Package 2 - 36 Avenue on the Astoria Line Construction $64,441,489 $64,441,489 0% Apr 2017 Apr 2017 2019 2019
Enhanced Station Initiative: Package 2 - 39 Avenue on the Astoria Line Construction $48,840,981 $48,840,981 0% Apr 2017 Apr 2017 2019 2019
Enhanced Station Initiative: Package 1 - Bay Ridge Avenue on the 4th Avenue Line   Complete   $40,924,957 $40,924,957 0% Nov 2016 Nov 2016 Nov 2017 Nov 2017
Enhanced Station Initiative: Package 1 - Prospect Avenue on the 4th Avenue Line   Complete   $38,358,432 $38,358,432 0% Nov 2016 Nov 2016 Nov 2017 Nov 2017
Enhanced Station Initiative: Package 1 - 53rd Street on the 4th Avenue Line   Complete   $40,861,519 $40,861,519 0% Nov 2016 Nov 2016 Nov 2017 Nov 2017
Repair of Elevated Street Stair at 238 Street on the Broadway-7 Avenue Line (SBMP) Construction $1,253,044 $1,196,520 (5%) Mar 2018 Mar 2018 2019
Repair of 2 Elevated Street Stairs at 215 Street on the Broadway-7 Avenue Line (SBMP) Construction $2,259,384 $2,259,384 0% Oct 2017 Oct 2017 2018
Repair of 2 Elevated Street Stairs at 215 Street on the Broadway-7 Avenue Line (SBMP) Construction $2,100,236 $2,100,236 0% Oct 2017 Oct 2017 2018
Repair of 2 Elevated Street Stairs at 238 Street on the Broadway-7 Avenue Line (SBMP) Construction $2,224,605 $2,589,592 16% Jul 2017 Jul 2017 2018
Repair of Platform Components at 125 Street on the Broadway-7 Avenue Line   Planning  $4,500,000 $4,500,000 0%
Repair of Subway Street Stairs at 34 Street on the Broadway Line (SBMP)   Planning  $1,945,801 $1,945,801 0% 2018 2018 2019 2019
Repair Subway Street Stair at 34 Street on the Broadway Line (SBMP)   Complete   $526,650 $526,650 0% Jun 2017 Jun 2017 Dec 2017 Dec 2017
Repair of Subway Street Stair at 34 Street on the Broadway Line (SBMP)   Complete   $867,713 $824,181 (5%) Jun 2017 Jun 2017 Jan 2018 Jan 2018
Repair of Subway Street Stair at 59 Street on the 4 Avenue Line (SBMP)   Complete   $642,690 $699,201 9% May 2017 May 2017 May 2018 May 2018
Enhanced Station Initiative: Package 3 - Ventilator Repairs at 163 Street on the 8 Avenue Line   Complete   $0 $1,186,105 0% Jul 2016 Jul 2016 Jan 2017 Jan 2017
Enhanced Station Initiative: Package 4 - Ventilator Repairs at 23 Street on the 6 Avenue Line   Complete   $1,458,419 $1,458,419 0% Jun 2016 Jun 2016 Dec 2016 Dec 2016
Enhanced Station Initiative: Package 5 - Ventilator Repairs at Clinton-Washington Avenues on the Fulton Line   Complete   $1,140,276 $1,140,276 0% Aug 2016 Aug 2016 Dec 2016 Dec 2016
Enhanced Station Initiative: Package 5 - Ventilator Repairs at Van Siclen Avenue on the Fulton Line   Complete   $1,631,711 $1,634,051 0% Oct 2016 Oct 2016 Aug 2017 Aug 2017
Enhanced Station Initiative: Package 5 - Ventilator Repairs at Classon Avenue on the Crosstown Line   Complete   $1,318,519 $1,320,530 0% Dec 2016 Dec 2016 Jul 2017 Jul 2017
Enhanced Station Initiative: Package 6 - Ventilator Repairs at Hunts Point Avenue on the Pelham Line   Complete   $881,568 $881,568 0% Aug 2016 Aug 2016 Jul 2017 Jul 2017
Enhanced Station Initiative: Package 8 - Ventilator Repairs at 167 Street on the Concourse Line   Complete   $1,851,310 $1,851,310 0% Feb 2017 Feb 2017 2017 May 2018
Enhanced Station Initiative: Package 3 - 163 St -Amsterdam Ave on 8th Avenue Line Construction $42,137,533 $42,137,533 0% Oct 2017 Oct 2017 2018 2018
Enhanced Station Initiative: Package 3 - Cathedral Parkway on the 8th Avenue Line Construction $40,284,770 $40,284,770 0% Oct 2017 Oct 2017 2018 2018
Enhanced Station Initiative: Package 3 - 86 Street on the 8th Avenue Line Construction $39,212,708 $39,212,708 0% Oct 2017 Oct 2017 2018 2018
Enhanced Station Initiative: Package 3 - 72 Street on the 8th Avenue Line Construction $35,769,302 $35,769,302 0% Oct 2017 Oct 2017 2018 2018
Enhanced Station Initiative: Package 6 - Ventilator Repairs at 3 Avenue-138 Street on the Pelham Line   Complete   $4,134,241 $4,335,771 5% Jul 2016 Jul 2016 Dec 2017 Dec 2017
Enhanced Station Initiative: Package 4 - 57 Street on the 6th Avenue Line Construction $50,043,565 $50,043,565 0% 2017 Feb 2018 2018 2019
Enhanced Station Initiative: Package 4 - 23 Street on the 6th Avenue Line Construction $30,284,342 $30,284,342 0% 2017 Feb 2018 2018 2019
Enhanced Station Initiative: Package 4 - 28 Street on the Lexington Avenue Line Construction $32,647,822 $32,792,822 0% 2017 Feb 2018 2018 2019
Enhanced Station Initiative: Package 4 - 34th St-Penn Station on the 8th Avenue Line Construction $26,586,712 $26,447,293 (1%) 2017 Feb 2018 2018 2019
Enhanced Station Initiative: Package 7 - Parsons Boulevard on the Queens Boulevard Line  Superseded $0 $0 0%
Enhanced Station Initiative: Package 7 - 67 Avenue on the Queens Boulevard Line  Superseded $0 $0 0%
Enhanced Station Initiative: Package 7 - Northern Boulevard on the Queens Boulevard Line  Superseded $0 $0 0%
Enhanced Station Initiative: Package 8 - 174-175 Streets on the Concourse Line Construction $41,114,966 $41,070,008 0% Feb 2018 Feb 2018 2018 2019
Enhanced Station Initiative: Package 8 - 167 Street on the Concourse Line Construction $44,163,870 $44,100,023 0% Feb 2018 Feb 2018 2018 2019
Enhanced Station Initiative: Package 8 - 145 Street on the Lenox Line Construction $39,453,988 $39,450,922 0% Feb 2018 Feb 2018 2018 2019
Ventilator Water Remediation at 3 Avenue-138 Street on the Pelham Line   Design    $6,332,658 $6,228,676 (2%) 2019 2019 2020 2020
Repair Subway Street Stair at Bowery on the Nassau Loop (SBMP) Construction $0 $722,084 0% Jul 2018 Jul 2018 2019
Repair Subway Street Stairs at 14 Street on the 6 Avenue Line (SBMP)   Planning  $0 $2,204,867 0% 2020 2020
Repair Subway Street Stair at 2 Avenue on the 6 Avenue Line (SBMP) Construction $0 $748,898 0% Sep 2018 Sep 2018 2019
Repair Subway Street Stair at Carroll Street on the 6 Avenue Line (SBMP) Construction $0 $930,579 0% Sep 2018 Sep 2018 2019
Repair Subway Street Stair at Church Avenue on the 6 Avenue Line (SBMP) Construction $0 $739,059 0% Sep 2018 Sep 2018 2019
Repair Subway Street Stair at Bergen Street on the Eastern Parkway Line (SBMP) Construction $0 $897,131 0% Sep 2018 Sep 2018 2019
Repair Subway Street Stair at Sterling Street on the Nostrand Line (SBMP) Construction $0 $963,229 0% Sep 2018 Sep 2018 2019
Repair Subway Street Stair at Winthrop Street on the Nostrand Line (SBMP) Construction $0 $726,033 0% Sep 2018 Sep 2018 2019
Repair Subway Street Stairs at 155 Street on the 8 Avenue Line (SBMP) Construction $1,406,203 $1,406,203 0% Jul 2018 Jul 2018 2019 2019
Repair Subway Street Stairs at Franklin Street on the Broadway-7 Avenue Line (SBMP) Construction $992,850 $1,263,266 27% Jul 2018 Jul 2018 2019
Repair Subway Street Stair at 14 Street on the Broadway-7 Avenue Line (SBMP) Construction $868,801 $868,801 0% Jun 2018 Jun 2018 2019 2019
Repair Subway Street Stair at 79 Street on the Broadway-7 Avenue Line (SBMP) Construction $776,500 $912,403 18% Jul 2018 Jul 2018 2019
Renewal of 95 Street Station on the 4 Avenue Line   Planning  $15,000,000 $15,000,000 0%
Repair 3 Subway Street Stairs at 57 Street on the Broadway Line (SBMP)   Planning  $0 $1,500,000 0% 2018 2018
Repair 1 Subway Street Stair at 57 Street on the Broadway Line (SBMP)   Planning  $0 $500,000 0% 2018 2018 2019 2019
Repair 3 Subway Street Stairs at 57 Street on the Broadway Line (SBMP) Construction $0 $2,180,731 0% Sep 2018 Sep 2018 2019
Repair Subway Street Stairs at Vernon Blvd - Jackson Av on the Flushing Line (SBMP) Construction $0 $1,491,019 0% Jul 2018 Jul 2018 2019 2019
Repair 1 Subway Street Stair at Grand Ave - Newtown on the Queens Blvd Line (SBMP)   Planning  $0 $888,127 0% Sep 2018 Sep 2018 2019 2019
Repair Subway Street Stairs at Kingsbridge Road on the Concourse Line (SBMP) Construction $0 $934,667 0% Jul 2018 Jul 2018 2019 2019
Repair 1 Subway Street Stair at Fulton St on the Crosstown Line (SBMP) Construction $0 $718,581 0% Jul 2018 Jul 2018 2019 2019
Repair Elevated Street Stairs at Brighton Beach on the Brighton Line (SBMP)   Planning  $0 $710,436 0% 2018 2018
Repair Elevated Street Stairs at Ocean Pkwy on the Brighton Line (SBMP)   Planning  $0 $1,286,235 0% 2018 2018
Platform Structural Repairs at 14 St-Union Square Station on the Canarsie Line Construction $0 $1,974,938 0% Sep 2018 2020
Disabled Accessibility
ADA Accessibility at Bedford Avenue Station on the Canarsie Line Construction $77,564,178 $77,705,330 0% 2016 Apr 2017 2020
ADA Accessibility at Astoria Boulevard Station on the Astoria Line Construction $49,877,653 $42,606,261 (15%) 2017 Jun 2018 2020
ADA Accessibility at Bedford Park Boulevard Station on the Bronx Concourse Line Construction $33,907,817 $34,238,141 1% 2016 Apr 2018 2020
ADA Accessibility at 86 Street Station on the 4 Avenue Line Construction $32,279,066 $32,279,066 0% Dec 2017 Dec 2017 2020
ADA Accessibility at Gun Hill Road Station on the Dyre Line Construction $56,915,512 $57,836,700 2% 2016 Apr 2018 2020
ADA Accessibility at Eastern Parkway-Brooklyn Museum Station on the Eastern Parkway Line Construction $54,743,565 $42,783,911 (22%) 2017 Aug 2018 2020
ADA Accessibility at Times Square Shuttle - Phase 3   Design    $237,088,001 $237,088,001 0% 2017 2018 2022
ADA Accessibility at Chambers Street Station on the Nassau Loop Construction $57,146,272 $47,343,486 (17%) 2017 Aug 2018 2020
ADA Accessibility at Greenpoint Avenue Station on the Crosstown Line Construction $44,878,630 $41,345,663 (8%) Jun 2018 Jun 2018 2020
ADA Accessibility at 59 Street Station on the 4 Avenue Line   Design    $63,316,171 $63,155,566 0% 2018 2018 2021
ADA Accessibility at Rockaway Parkway Station on the Canarsie Line   Design    $10,849,294 $10,849,294 0% 2016 2018 2020
ADA Accessibility at 1st Avenue Station on the Canarsie Line Construction $44,899,084 $44,899,084 0% 2016 Apr 2017 2020
ADA Accessibility at Court Square Station on the Crosstown Line   Design    $16,629,039 $16,629,039 0% 2016 2020
ADA Accessibility at 149 Street-Grand Concourse Complex   Design    $85,000,000 $85,000,000 0% 2017 2019
ADA Accessibility at Woodhaven Boulevard Station on the Jamaica Line   Planning  $35,000,000 $35,000,000 0% 2017 2019 2022
ADA Systemwide Study   Design    $10,000,000 $10,000,000 0% Oct 2017 Oct 2017 2020
Visual Identification of ADA Boarding Areas Pilot   Planning  $150,000 $150,000 0% 2017
ADA Accessibility at Livonia Avenue-Junius Street  Superseded $0 $399,943 0% 2018
ADA Accessibility at Court Square Station on the Crosstown Line - Stair Phase   Complete   $13,088,889 $13,050,889 0% 2016 Mar 2017 Jun 2018
ADA Accessibility and Renewal at 77 St Station on the 4th Avenue Line - Design Only   Planning  $5,000,000 $5,000,000 0%
ADA Accessibility at 95 St Station on the 4th Avenue Line   Planning  $35,000,000 $35,000,000 0% 2020 2023
ADA Accessibility at 57 St Station on the Broadway Line: Additional Support Costs Construction $49,237,443 $45,737,443 (7%) Dec 2017 Dec 2017 2020 2021
ADA Accessibility at 68 St-Hunter College Station on the Lexington Av Line: Additional Support Costs   Planning  $47,962,008 $47,962,008 0% 2017 2019 2021 2022
ADA Accessibility at Times Square Shuttle - Phase 3 (SBDP)   Planning  $5,000,000 $5,000,000 0%
ADA Accessibility and Station Improvements at Westchester Square Station on the Pelham Line   Planning  $90,000,000 $90,000,000 0%
ADA Enhancements at Various Locations   Planning  $200,000,000 $198,025,000 (1%)
ADA Accessibility at 14 Street - 6 Avenue / 7 Avenue Station Complex - Design Only   Design    $0 $4,619,143 0% 2018 2019
ADA / Station Capacity Enhancements at 170 Street Station on the Jerome Line   Design    $0 $1,975,000 0%
Other Station Improvements
Station Signage at Various Locations Construction $10,775,787 $10,775,787 0% Jun 2016 Jun 2016 2020
Access Improvements: Grand Central, Phase 2 Construction $75,000,000 $75,000,000 0% 2017 Sep 2016 2020
Station Entrance and Structural Work at 8 Avenue on the Sea Beach Line Construction $16,334,981 $16,334,981 0% 2016 Aug 2017 2018
Reconstruction of Times Square Shuttle - Phase 3   Design    $29,354,906 $29,354,906 0% 2017 2018 2022
Water Condition Remedy - 2015 Construction $8,130,532 $8,530,532 5% 2016 Dec 2015 2018
Station Railings   Design    $3,750,597 $3,750,597 0% 2016 2018
Station Condition Survey Update   Complete   $8,904,817 $8,959,527 1% 2015 Jan 2017 Jun 2018
Water Condition Remedy - 2017   Design    $5,237,719 $4,927,819 (6%) 2018 2018 2020
Reconstruct Cortlandt Street Station - Broadway-7th Avenue Line Construction $71,800,000 $71,800,000 0% Apr 2015 Apr 2015 2018
Improvements to the Church Street Corridor Construction $30,000,000 $30,000,000 0% 2015 Jan 2014 2018
New Street Stairs at 2 Locations on the Canarsie Line Construction $7,205,736 $7,264,592 1% 2016 Apr 2017 2020
Study for 42nd Street Shuttle  Superseded $0 $0 0% 2015
Livonia Avenue - Junius Street Station Connector  Superseded $0 $399,943 0% 2018
Station Capacity Enhancements at Myrtle Avenue on the Jamaica Line   Design    $6,563,787 $6,269,814 (4%)
Circulation Improvements at Union Square on the Canarsie Line Construction $15,000,000 $17,592,340 17% Sep 2018 Sep 2018 2020
Planning & Engineering Study at Sutphin Blvd-Archer Av   Planning  $10,000,000 $7,000,000 (30%)
Station Capacity Enhancements at Metropolitan Avenue on the Crosstown Line Construction $1,436,213 $1,730,186 20% Sep 2018 2019
Station Capacity Enhancements at Broadway Junction on the Jamaica Line Construction $10,206,130 $10,787,201 6% Apr 2018 Apr 2018 2019
Station Capacity Enhancements at Marcy Avenue on the Jamaica Line Construction $12,921,063 $12,935,407 0% Mar 2018 Mar 2018 2019 2019
Station Circulation Enhancements at Various Locations   Planning  $100,000,000 $100,000,000 0%
Fare Control Upgrade at Sutphin Boulevard-Archer Avenue-JFK Airport on the Archer Avenue Line (SBDP)   Design    $0 $3,000,000 0%
Number of Projects for New York City Transit = 215