Capital Plan 2015 - 2019  
New York City Transit  
Buses   Budget   Schedule  


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Bus Replacement
Purchase 628 Standard Diesel Buses - Design Only   Complete   $397,784,818 $300,000 (100%) May 2016 May 2016 Jun 2017
Purchase 138 Standard CNG Buses Construction $85,050,000 $94,296,001 11% Jan 2016 Jan 2016 2017
Purchase 275 Hybrid-Electric Standard Buses   Planning  $127,795,056 $265,677,519 108% 2019 2019 2021
Purchase (0) Standard Hybrid-Electric Buses  Superseded $66,971,027 $0 (100%) 2019
Purchase 180 Diesel and 10 Hybrid Articulated Buses   Design    $168,297,225 $193,810,446 15% 2017 2018 2020
Purchase 50 Express Buses   Planning  $36,556,270 $38,810,476 6% 2019 2020 2022
Depot Bus Location System   Planning  $6,400,000 $6,400,000 0% 2016 2018 2020
Automatic Passenger Counting - Pilot & Phase 1   Planning  $5,673,941 $5,590,885 (1%) 2016 2017 2019
Purchase 110 CNG Articulated Buses Construction $106,404,033 $106,404,033 0% 2016 Apr 2017 2018
Automatic Vehicle Location Monitoring (AVLM) for Paratransit Vehicles   Design    $19,021,090 $19,021,090 0% 2016 2019 2021
Purchase 50 Electric Buses and 8 Charging Stations   Planning  $0 $71,411,393 0%
Replace Integrated Farebox Unit (IFU) Components   Planning  $0 $11,818,000 0%
Purchase 251 Standard Diesel Buses Construction $0 $161,041,149 0% Jun 2017 Jun 2017 2019
Purchase 367 Standard Diesel and 10 Hybrid-Electric Buses Construction $0 $235,733,576 0% Jun 2017 Jun 2017 2019
Number of Projects for New York City Transit = 14