Projects with No Budget Changes
Capital Plan 2015 - 2019 
SIRTOA  Budget  Schedule 


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Staten Island Railway
UHF T-Band Radio System Replacement Design $25,701,491 $25,701,491 0% 2018 2018 2021
Installation of Customer Information Signs Construction $1,151,200 $1,151,200 0% 2015 Aug 2016 2017
Station Component Program (SBDP) Planning $5,000,003 $5,000,003 0% 2017 2018
Rehabilitation of Amboy Road Bridge Design $5,857,658 $5,857,658 0% 2015 2018
Relocation of Headquarters to Clifton Shop Construction $10,000,000 $10,000,000 0% Dec 2016 Dec 2016 2020
Enhanced Station Initiative: Richmond Valley Planning $0 $15,330,239 0% 2018 2018 2019 2019
Number of Projects for SIRTOA = 6