Capital Plan 2015 - 2019  
Metro-North Railroad   Budget   Schedule  


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Track And Structures
Cyclical Track Program   Complete   $23,600,000 $23,600,000 0% 2019 Dec 2016 Jun 2018
Systemwide Drainage   Complete   $2,770,000 $2,770,000 0% 2016 Nov 2015 Nov 2017
Repair Park Avenue Viaduct at 118 St   Complete   $0 $0 0% Jul 2016 Nov 2016
West of Hudson Track Improvements   Complete   $10,000,000 $10,000,000 0% 2015 Aug 2016 Dec 2017
Miscellaneous
Railroad Protective Liability   Complete   $4,500,000 $3,783,905 (16%) Jun 2016 Jun 2016 May 2017
Number of Projects for Metro-North Railroad = 5