Capital Plan 2015 - 2019  
Metro-North Railroad   Budget   Schedule  


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Track And Structures
Systemwide Drainage   Complete   $8,000,000 $2,770,000 (65%) 2016 Nov 2015 Nov 2017
Repair Park Avenue Viaduct at 118 St   Complete   $0 $0 0% Jul 2016 Nov 2016
West of Hudson Track Improvements   Complete   $10,000,000 $10,000,000 0% 2015 Aug 2016 Dec 2017
Miscellaneous
Railroad Protective Liability   Complete   $4,500,000 $4,500,000 0% Jun 2016 Jun 2016 May 2017
Number of Projects for Metro-North Railroad = 4