Capital Plan 2015 - 2019 
Metro North Railroad 
Power   Budget  Schedule 


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Power
Replace MA's in Signal Substations   Planning  $21,153,435 $21,153,435 0% 2017 2018 2021
Transformer Rehabilitation   Planning  $3,200,000 $3,200,000 0% 2019 2018 2020
Replace AC Circuit Breaker/Switchgear   Planning  $3,900,000 $3,900,000 0% 2018
Harlem & Hudson Power Rehabilitation   Planning  $15,000,000 $15,000,000 0% 2015 2018 2021
Harlem and Hudson Power Improvements   Design    $21,400,000 $21,400,000 0% 2017 2018 2020
Three Substation Replacements **   Planning  $12,000,000 $12,000,000 0% 2019
3rd Rail Component Replacement  Superseded $0 $0 0% 2017 2019 2019
Replace 3rdRail Sectionalizing Switches   Planning  $428,015 $428,015 0% 2017 2019 2019
Replace Substations 128 and 178 **   Planning  $2,750,000 $2,750,000 0% 2017 2018 2021
Park Avenue Tunnel Alarm   Planning  $22,000,000 $22,000,000 0% 2016
Replace Tunnel Lighting  Superseded $0 $0 0% 2016
Mentoring - Power  Superseded $0 $0 0% 2016
Harlem & Hudson line Power Improvements (86th St / 110th St) Construction $10,000,000 $10,000,000 0% Mar 2014 Mar 2019
Number of Projects for Metro North Railroad = 13