Capital Plan 2015 - 2019 
Long Island Rail Road 
Power   Budget  Schedule 


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Power
Station Replacement Construction $59,130,000 $59,130,000 0% 2017 Mar 2016 Mar 2022
Substation Components Construction $38,850,000 $38,850,000 0% 2018 Apr 2016 Feb 2022
3Rd Rail - 2000 Million Cubic Meter Cable Construction $2,400,000 $2,400,000 0% 2017 Mar 2016 Dec 2019
3Rd Rail - Disconnect Switches Construction $1,600,000 $1,600,000 0% 2017 Mar 2016 Dec 2019
3Rd Rail - Protection Board Construction $8,800,000 $8,800,000 0% 2017 Mar 2016 Dec 2019
3Rd Rail - Composite Rail Construction $11,150,000 $11,150,000 0% 2018 Mar 2016 Dec 2019
3Rd Rail - Feeder Cable Replacement Construction $3,200,000 $3,200,000 0% 2018 Mar 2016 Dec 2019
Negative Reactor Upgrade Construction $3,200,000 $3,200,000 0% 2017 Jun 2016 Dec 2019
Substation Battery Replacement Construction $800,000 $800,000 0% Jun 2016 Jun 2016 Oct 2019
Signal Power Motor Generator Replacement Construction $6,400,000 $6,400,000 0% 2017 Jun 2016 Sep 2020
DC Relay Controls Replacement Construction $1,600,000 $1,600,000 0% Apr 2016 Apr 2016 Dec 2019
Signal Power Line Replacement Construction $3,200,000 $3,200,000 0% 2018 Apr 2016 Dec 2019
Power Pole Replacement Construction $3,200,000 $3,200,000 0% 2018 Mar 2016 Dec 2019
Atlantic Avenue Tunnel Lightning Construction $5,000,000 $5,000,000 0% Mar 2017 Mar 2017 Dec 2020
4,160 Volt Feeders Construction $1,600,000 $1,600,000 0% 2017 May 2016 Dec 2019
New Substations   Design    $5,000,000 $5,000,000 0% 2018 Apr 2017 Dec 2019
Substation Renewals   Planning  $0 $0 0% 2017
Number of Projects for Long Island Rail Road = 17