Bridges and Tunnels   Projects with Increases or Decreases Between (9.99%) and 9.99%  
      Budget   Schedule  


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Structures
Design for The Structural Rehabilitation of Manhattan Entrance Plaza and Queens Plaza - Queens Midtown Tunnel Planning $30,000 $29,906 0% 2016 2020 2018 2022
Study and Monitoring for the Rehabilitation of the Queens Anchorage at the Robert F. Kennedy Bridge Design $2,435,725 $2,656,364 9% Mar 2016 Mar 2016 2020 Sep 2021
Toll Plazas & Atms
Develop a comprehensive and effective Traffic and Incident Management System by building upon the current Transmit and Video Detection Systems Planning $2,984,141 $2,949,843 (1%) 2017 2019 2020 2021
Replacement and Upgrade of Existing Toll Systems and Exploration of Future Tolling Technologies and Systems Construction $92,392,796 $92,427,094 0% 2017 2016 2021 2021
Implement Open Road Tolling (ORT) /Cashless Tolling on Robert F. Kennedy Bridge Construction $99,727,547 $99,753,884 0% Oct 2016 Oct 2016 Jun 2017 Jun 2017
Buildings & Sites
Rehabilitation of Robert Moses Building and Ancillary Facilities on Randall's Island Planning $43,811,037 $39,602,482 (10%) 2019 2019 2020 2020
Miscellaneous
Miscellaneous Design $5,449,756 $4,969,756 (9%) Jun 2016 Jun 2016 2019 2019
Number of Projects for MTA Bridges & Tunnels = 7