Capital Plan 2015 - 2019  
Bridges and Tunnels   Budget   Schedule  


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Structures
Design development and study for Phase II - Tunnel Improvements and Modernization of the Brooklyn-Battery (Hugh L. Carey) and Queens Midtown Tunnels   Planning  $5,068,621 $5,068,621 0% Sep 2017 Dec 2019 2019 Dec 2021
Study for Physical Barriers to Enhance Public Safety on Suspension Bridges  Superseded $0 $0 0% 2019 2019 2022 2022
Tower and Pier Fender Protection System - Bronx-Whitestone Bridge   Design    $19,300,000 $19,300,000 0% 2018 2018 2020 2020
Miscellaneous Structural Rehabilitation: Steel repairs and Removal of Tuned Mass Damper - Bronx-Whitestone Bridge Construction $20,259,038 $20,259,038 0% Dec 2015 Dec 2015 Feb 2019 Dec 2018
Monitoring, Inspection and Testing of the Bronx-Whitestone Bridge's Main Cable and Cable Wires Construction $10,463,325 $10,463,325 0% Dec 2015 Dec 2015 Feb 2019 Dec 2018
Replacement and Upgrade of Bridge Fender System at Cross Bay and Marine Parkway Bridges and Scour Protection at the Cross Bay Bridge   Design    $48,912,294 $48,912,294 0% 2018 2018 2020 2020
Development of Conceptual Designs for Long Term Needs at Cross Bay and Marine Parkway Bridges  Superseded $0 $0 0% 2018 2020 2022 2024
Design for Phase III - Future Repair and Rehabilitation of Tunnel Leaks, Spalls, Finishes at the Hugh L. Carey Tunnel  Superseded $0 $0 0% 2019 2020 2023 2023
Design for Future Rehabilitation and Replacement of the Manhattan Plaza of the Hugh L. Carey Tunnel  Superseded $0 $0 0% 2019 2020 2023 2023
Structural Rehabilitation Phase II - Henry Hudson Bridge   Design    $23,686,921 $23,686,921 0% 2019 2019 2021 2021
Rehabilitation of Skewbacks - Henry Hudson Bridge Construction $100,443,950 $100,443,950 0% May 2017 May 2017 2019 Jan 2020
Design for The Structural Rehabilitation of Manhattan Entrance Plaza and Queens Plaza - Queens Midtown Tunnel   Planning  $30,000 $29,906 0% 2016 2020 2018 2022
Conceptual Design for miscellaneous Tunnel Structural Repairs - Queens Midtown Tunnel  Superseded $0 $0 0% 2016 2020 2021 2021
Study and Monitoring for the Rehabilitation of the Queens Anchorage at the Robert F. Kennedy Bridge   Design    $2,435,725 $2,656,364 9% Mar 2016 Mar 2016 2020 Sep 2021
Design and Construct Seismic and Wind Retofits for the Suspension Span of the Robert F. Kennedy Bridge   Design    $68,206,486 $68,206,486 0% 2019 2019 2022 2023
Monitoring, Inspection and Testing of the Robert F. Kennedy Queens Suspension Bridge Main Cable and Cable Wires   Design    $16,342,037 $16,342,037 0% 2019 2019 2021 2023
Construction of Interim Repairs for the FDR Ramp Construction $25,900,000 $19,700,000 (24%) Nov 2017 Dec 2017 2020 Jun 2019
Miscellaneous Structural Rehabilitation at the Robert F. Kennedy Bridge   Design    $93,753,884 $93,753,884 0% 2019 2019 2022 2023
Design and Construction of Superstructure Repairs on the Throgs Neck Bridge Approach Viaducts   Design    $162,451,034 $162,451,034 0% 2018 2018 2022 2021
Design for Anchorage and Main Tower protection at the Throgs Neck Bridge   Design    $6,658,493 $6,658,493 0% 2017 2018 2020 2023
Design and construction for the rehabilitation of the exterior and interior of the Anchorages at the Verrazano-Narrows Bridge   Design    $48,988,596 $48,988,596 0% 2018 2018 2021 2021
Miscellaneous Steel Repair and Concrete Rehabilitation - Verrazano-Narrows Bridge   Design    $33,811,737 $33,811,737 0% 2019 2019 2021 2021
Verrazano-Narrows Bridge Main Cable Testing - Phase I Construction $43,130,298 $31,360,586 (27%) Nov 2017 Dec 2017 Jun 2020 Jun 2020
Restoration of the Granite Fašade and Tower Pier Foundation and Relocation of the FDNY Mooring Platform - Verrazano-Narrows Bridge   Design    $21,763,164 $24,286,088 12% 2018 2018 2020 2020
Roadways & Decks
Agency-Wide: Planning/Strategic Initiatives Construction $10,000,000 $13,987,916 40% 2019 Oct 2017 2021 Dec 2017
Construct a New Northbound Connector Ramp from Harlem River Lift Span to Harlem River Drive - Robert F. Kennedy Bridge   Design    $135,360,574 $135,360,574 0% 2019 2019 2021 2022
Final design and construction of Ramp Rehabilitation at the Manhattan Plaza of the Robert F. Kennedy Bridge Construction $35,056,243 $35,056,243 0% 2019 Feb 2017 2023 Jul 2017
Replacement of the Suspended Span Deck at the Throgs Neck Bridge   Planning  $305,885,018 $305,885,018 0% 2018 2018 2021 2023
Study for the replacement of Bronx and Queens Approach Viaducts of the Throgs Neck Bridge   Design    $12,820,889 $12,820,889 0% May 2017 May 2017 2021 Aug 2020
Design and Construction for Widening of the Verrazano-Narrows Bridge approach to the Gowanus Expressway   Design    $31,142,845 $31,142,845 0% 2019 2019 2021 2021
Study and preliminary design for the replacement of the Lower Level Suspended Span Deck - Verrazano-Narrows Bridge   Planning  $6,658,493 $6,658,493 0% 2018 2018 2021 2021
Design for the Verrazano-Narrows Bridge replacement of Upper Level Approaches in Brooklyn and Staten Island, Replacement and Widening of Existing Lower and Upper Level Ramps and Construction of Phase I   Design    $286,015,434 $286,015,434 0% 2019 2019 2023 2023
Design for the widening of Belt Parkway - Verrazano-Narrows Bridge   Planning  $4,635,066 $4,635,066 0% 2017 2018 2020 2021
Toll Plazas & Atms
Installation of Rotating Prism Signs (RPS) at the Bronx-Whitestone, Throgs Neck and Verrazano-Narrows Bridges   Complete   $244,308 $3,030,133 1,140% Dec 2015 Dec 2015 Dec 2017 Dec 2017
Install and Integrate IP traffic cameras at all B & T facilities   Planning  $10,704,196 $10,704,196 0% 2019 2019 2022 2022
Develop a comprehensive and effective Traffic and Incident Management System by building upon the current Transmit and Video Detection Systems   Planning  $2,984,141 $2,949,843 (1%) 2017 2019 2020 2021
Replacement and upgrade of existing Advanced Management System (ATMS) and subsystems at all Nine Facilities and Operations Control and Command Center (OCCC)   Planning  $8,111,891 $8,111,891 0% 2018 2018 2020 2020
Replacement and Upgrade of Existing Toll Systems and Exploration of Future Tolling Technologies and Systems Construction $92,392,796 $92,427,094 0% 2017 2016 2021 2021
Rehabilitation/Upgrades to Toll Plaza Structural Elements Construction $42,481,121 $42,481,121 0% 2017 2017 2022 2022
Implement Open Road Tolling (ORT) /Cashless Tolling on Bronx-Whitestone Bridge Construction $44,293,560 $44,293,560 0% Mar 2017 Mar 2017 Oct 2017 Oct 2017
Implement Open Road Tolling (ORT) /Cashless Tolling on Cross Bay Bridge Construction $18,064,320 $18,064,320 0% Mar 2017 Mar 2017 Apr 2017 Apr 2017
Implement Open Road Tolling (ORT) /Cashless Tolling on Hugh L Carey Tunnel Construction $25,038,179 $25,038,179 0% Nov 2016 Nov 2016 Jan 2017 Jan 2017
Open Road Tolling / Aesthetics   Planning  $7,660,540 $7,660,540 0%
Construction for the replacement of the decks and supporting structure on the Upper Level, the Lower Level South Approach Deck, and the Concrete Cellular Structure including the maintenance garage - Henry Hudson Bridge Construction $101,466,744 $101,466,744 0% Apr 2017 Apr 2017 May 2021 May 2021
Implement Open Road Tolling (ORT) /Cashless Tolling on Marine Parkway Bridge Construction $18,427,760 $18,427,760 0% Mar 2017 Mar 2017 Apr 2017 Apr 2017
Implement Open Road Tolling (ORT) /Cashless Tolling on Queens Midtown Tunnel Construction $35,612,483 $35,612,483 0% Nov 2016 Nov 2016 Jan 2017 Jan 2017
Implement Open Road Tolling (ORT) /Cashless Tolling on Robert F. Kennedy Bridge Construction $99,727,547 $99,753,884 0% Oct 2016 Oct 2016 Jun 2017 Jun 2017
Implement Open Road Tolling (ORT) /Cashless Tolling on Throgs Neck Bridge Construction $50,845,446 $50,845,446 0% Mar 2017 Mar 2017 Apr 2017 Apr 2017
Implement Open Road Tolling (ORT) /Cashless Tolling on Verrazano- Narrows Bridge Construction $67,369,025 $67,369,025 0% Mar 2017 Mar 2017 Apr 2017 Apr 2017
Utilities
Design for the replacement of facility monitoring and safety systems  Superseded $0 $0 0% 2019 2019 2020 2020
Advanced Traveler Information Systems   Planning  $1,249,791 $1,249,791 0% 2017 2017 2020 2020
Install Prototype LED Roadway Display Signs on RFK Bridge. After successful testing install on Bronx-Whitestone, Throgs Neck, Verrazano-Narrows, and Robert F. Kennedy Bridges Construction $10,000,005 $10,000,005 0%
Study for structural health monitoring systems and prototype installation   Planning  $9,126,006 $9,126,006 0% 2019 2019 2022 2022
Installation of a fire standpipe system from the Bronx and Queens Tower pedestal to the roadway level - Bronx-Whitestone Bridge   Design    $7,283,816 $7,283,816 0% 2018 2018 2020 2020
Installation of an Integrated Facility Monitoring and Detection System - Bronx-Whitestone Bridge Construction $29,851,707 $36,220,810 21% Dec 2017 Dec 2017 2019 Dec 2020
Rehabilitation of the Tunnel Ventilation Systems - Hugh L. Carey Tunnel   Planning  $85,475,761 $85,475,761 0% 2018 2018 2021 2021
Replacement and upgrade of existing smoke/fire detection systems in the ventilation building and service building - Hugh L. Carey Tunnel   Planning  $10,577,411 $10,577,411 0% 2018 2018 2020 2020
Rehabilitation of the Brooklyn Service Building electrical distribution room - Hugh L. Carey Tunnel   Planning  $7,329,049 $7,329,049 0% 2018 2018 2020 2020
Replacement and upgrades of the lighting system on the approach Parkways - Henry Hudson Bridge Construction $14,085,742 $14,085,742 0% Apr 2017 Apr 2017 Jan 2021 Jan 2021
Replacement and Upgrade of Substations - Henry Hudson Bridge   Planning  $2,122,070 $2,122,070 0% 2019 2021
Rehabilitation of the tunnel controls and communication systems - Queens Midtown Tunnel   Planning  $42,196,192 $42,196,192 0% 2018 2018 2021 2021
Installation of smoke/fire detection systems in the ventilation building and service building - Queens Midtown Tunnel   Planning  $7,049,714 $7,049,714 0% 2018 2018 2020 2020
Rehabilitation and Upgrade of Electrical and Mechanical Systems on The Harlem River Lift Span - Robert F. Kennedy Bridge   Design    $21,972,660 $21,972,660 0% 2017 2017 2020 2020
Installation of a Dry Fire Standpipe System on the Randall's Island/Ward's Island Viaduct, Bronx Plaza, Harlem River Lift Span and Bronx Truss Span - Robert F. Kennedy Bridge   Design    $22,609,524 $22,609,524 0% 2016 Mar 2017 Dec 2019 Dec 2019
Installation of an Integrated Electronic Facility Monitoring and Detection System - Robert F. Kennedy Bridge Construction $42,354,011 $52,103,140 23% Dec 2017 Dec 2017 2019 Dec 2020
Relocation of the 13KV substation on Randall's Island - Robert F. Kennedy Bridge   Planning  $35,090,000 $25,709,946 (27%) 2018 2018 2020 2020
Service Building Fire Alarm Upgrade -Throgs Neck Bridge   Design    $1,328,961 $1,328,961 0% 2018 2020
Design for the Replacement of the Electrical Equipment and Rehabilitation of the Tower Elevator - Throgs Neck Bridge   Planning  $2,757,675 $2,757,675 0% 2019 2019 2021 2021
Construction of an Anchorage Dehumidification System - Throgs Neck Bridge Construction $43,547,419 $43,547,419 0% Dec 2015 Dec 2015 Jun 2018 Jun 2018
Rehabilitate Tower Elevators at the Verrazano-Narrows Bridge   Planning  $8,631,633 $11,528,010 34% 2019 2020 2021 2021
Buildings & Sites
Agency-wide hazardous materials abatement   Design    $10,650,000 $10,650,000 0% 2017 2017 2020 2020
Replacement of the Operations Command and Control Center (OCCC)   Design    $26,308,446 $26,308,446 0% 2018 2018 2020 2020
Design for the architectural and structural rehabilitation of ventilation buildings - Hugh L. Carey Tunnel   Planning  $4,726,946 $4,726,946 0% 2017 2017 2019 2019
Design for the architectural and structural Rehabilitation of Ventilation Buildings - Queens Midtown Tunnel   Planning  $3,172,204 $3,172,204 0% 2017 2017 2019 2019
Rehabilitation of Robert Moses Building and Ancillary Facilities on Randall's Island   Planning  $43,811,037 $39,602,482 (10%) 2019 2019 2020 2020
Miscellaneous
Enterprise Asset Management Program Construction $4,000,000 $4,000,000 0% May 2016 May 2016 2019 2019
MTA Independent Engineering services   Design    $2,471,873 $2,471,873 0% May 2016 May 2016 2020 2020
All Agency Protective Liability Insurance   Design    $13,090,835 $13,090,835 0% Jun 2016 Jun 2016 2020 2020
Program Administration   Design    $17,600,000 $21,080,165 20% Sep 2015 Sep 2015 Dec 2019 Dec 2019
Miscellaneous   Design    $5,449,756 $4,969,756 (9%) Jun 2016 Jun 2016 2019 2019
Scope Development   Design    $12,478,968 $12,478,968 0% Nov 2016 Nov 2016 2020 2020
Traffic Enforcement Support   Planning  $7,800,000 $7,800,000 0% Jun 2016 Jun 2016 Dec 2019 Dec 2019
Small Business Mentoring Program   Design    $3,671,039 $3,671,039 0% Jun 2016 Jun 2016 Jun 2020 Jun 2020
Structural Painting
Miscellaneous Agency-Wide painting   Planning  $14,315,898 $14,315,898 0% Oct 2016 Oct 2016 Dec 2019 Dec 2019
Painting of the Tower Interior Base Cells and Struts - Bronx-Whitestone Bridge Construction $32,987,418 $32,987,418 0% Dec 2015 Dec 2015 Feb 2019 Feb 2019
Replacement of the Overcoat Paint System - Henry Hudson Bridge   Design    $20,636,784 $20,636,784 0% 2019 2019 2021 2021
Painting of the Suspended Span/Bronx Truss Steel - Robert F. Kennedy Bridge   Planning  $32,114,200 $32,114,200 0% 2019 2019 2023 2023
Painting of the Suspended Span Steel and Tower Base cells - Throgs Neck Bridge   Planning  $25,992,747 $25,992,747 0% 2018 2018 2021 2021
Painting of the Anchorages Interior - Throgs Neck Bridge Construction $8,218,139 $8,218,139 0% Dec 2015 Dec 2015 Jun 2018 Jun 2018
Painting of the Suspended Span Upper and Lower Level Steel - Verrazano-Narrows Bridge   Planning  $41,706,554 $41,706,554 0% 2018 2018 2021 2021
Number of Projects for Bridges and Tunnels = 90