Capital Plan 2015 - 2019  
Bridges and Tunnels   Budget   Schedule  


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Structures
Tower and Pier Fender Protection System - Bronx-Whitestone Bridge   Design    $19,300,000 $19,300,000 0% 2018 2019 2020 2022
Replacement and Upgrade of Bridge Fender System at Cross Bay and Marine Parkway Bridges and Scour Protection at the Cross Bay Bridge   Design    $48,912,294 $48,912,294 0% 2018 2018 2020 2020
Structural Rehabilitation Phase II - Henry Hudson Bridge   Design    $23,686,921 $23,686,921 0% 2019 2019 2021 2021
Study and Monitoring for the Rehabilitation of the Queens Anchorage at the Robert F. Kennedy Bridge   Design    $2,435,725 $2,656,364 9% Mar 2016 Mar 2016 2020 Sep 2021
Design and Construct Seismic and Wind Retrofits for the Suspension Span of the Robert F. Kennedy Bridge   Design    $68,206,486 $68,206,486 0% 2019 2019 2022 2023
Monitoring, Inspection and Testing of the Robert F. Kennedy Queens Suspension Bridge Main Cable and Cable Wires   Design    $16,342,037 $16,342,037 0% 2019 2019 2021 2023
Miscellaneous Structural Rehabilitation at the Robert F. Kennedy Bridge   Design    $93,753,884 $93,753,884 0% 2019 2019 2022 2023
Design and Construction of Superstructure Repairs on the Throgs Neck Bridge Approach Viaducts   Design    $162,451,034 $162,451,034 0% 2018 2019 2022 2023
Design for Anchorage and Main Tower protection at the Throgs Neck Bridge   Design    $6,658,493 $6,658,493 0% 2017 2019 2020 2023
Design and construction for the rehabilitation of the exterior and interior of the Anchorages at the Verrazano-Narrows Bridge   Design    $48,988,596 $48,988,596 0% 2018 2018 2021 2021
Miscellaneous Steel Repair and Concrete Rehabilitation - Verrazano-Narrows Bridge   Design    $33,811,737 $33,811,737 0% 2019 2018 2021 2021
Restoration of the Granite Fašade and Tower Pier Foundation and Relocation of the FDNY Mooring Platform - Verrazano-Narrows Bridge   Design    $21,763,164 $24,286,088 12% 2018 2018 2020 2020
Roadways & Decks
Construct a New Northbound Connector Ramp from Harlem River Lift Span to Harlem River Drive - Robert F. Kennedy Bridge   Design    $135,360,574 $135,360,574 0% 2019 2019 2021 2022
Study for the replacement of Bronx and Queens Approach Viaducts of the Throgs Neck Bridge   Design    $12,820,889 $12,820,889 0% May 2017 May 2017 2021 Aug 2020
Design and Construction for Widening of the Verrazano-Narrows Bridge approach to the Gowanus Expressway   Design    $31,142,845 $31,142,845 0% 2019 2019 2021 2021
Design for the Verrazano-Narrows Bridge replacement of Upper Level Approaches in Brooklyn and Staten Island, Replacement and Widening of Existing Lower and Upper Level Ramps and Construction of Phase I   Design    $286,015,434 $286,015,434 0% 2019 2019 2023 2023
Utilities
Installation of a fire standpipe system from the Bronx and Queens Tower pedestal to the roadway level - Bronx-Whitestone Bridge   Design    $7,283,816 $7,283,816 0% 2018 2018 2020 2020
Rehabilitation and Upgrade of Electrical and Mechanical Systems on The Harlem River Lift Span - Robert F. Kennedy Bridge   Design    $21,972,660 $21,972,660 0% 2017 2017 2020 2020
Installation of a Dry Fire Standpipe System on the Randall's Island/Ward's Island Viaduct, Bronx Plaza, Harlem River Lift Span and Bronx Truss Span - Robert F. Kennedy Bridge   Design    $22,609,524 $22,609,524 0% 2016 Mar 2017 Dec 2019 Dec 2019
Service Building Fire Alarm Upgrade -Throgs Neck Bridge   Design    $1,328,961 $1,328,961 0% 2018 2020
Buildings & Sites
Agency-wide hazardous materials abatement   Design    $10,650,000 $10,650,000 0% 2017 2017 2020 2020
Replacement of the Operations Command and Control Center (OCCC)   Design    $26,308,446 $26,308,446 0% 2018 2018 2020 2020
Miscellaneous
MTA Independent Engineering services   Design    $2,471,873 $2,471,873 0% May 2016 May 2016 2020 2020
All Agency Protective Liability Insurance   Design    $13,090,835 $13,090,835 0% Jun 2016 Jun 2016 2020 2020
Program Administration   Design    $17,600,000 $17,600,000 0% Sep 2015 Sep 2015 Dec 2019 Dec 2019
Miscellaneous   Design    $5,449,756 $4,969,756 (9%) Jun 2016 Jun 2016 2019 2019
Scope Development   Design    $12,478,968 $12,478,968 0% Nov 2016 Nov 2016 2020 2020
Small Business Mentoring Program   Design    $3,671,039 $3,671,039 0% Jun 2016 Jun 2016 Jun 2020 Jun 2020
Structural Painting
Replacement of the Overcoat Paint System - Henry Hudson Bridge   Design    $20,636,784 $20,636,784 0% 2019 2019 2021 2021
Number of Projects for Bridges and Tunnels = 29