Capital Plan 2015 - 2019 
Bridges & Tunnels 
Structural Painting   Budget  Schedule 


Description


Photos


Phase
Latest
Amendment
Budget


Current
Latest Amendment
vs.
Current


Scope

Original
Start

Current
Start

Original
Completion

Current
Completion
Agency-Wide
Miscellaneous Agency-Wide painting   Planning  $4,044,384 $4,044,384 0% Oct 2016 Oct 2016 Dec 2019 Dec 2019
Bronx-Whitestone Bridge
Painting of the Tower Interior Base Cells and Struts - Bronx-Whitestone Bridge Construction $30,581,400 $30,581,400 0% Dec 2015 Dec 2015 Feb 2019 Dec 2018
Henry Hudson Bridge
Replacement of the Overcoat Paint System - Henry Hudson Bridge   Design    $20,636,784 $20,636,784 0% 2019 2019 2021 2021
Robert F. Kennedy Bridge
Painting of the Suspended Span/Bronx Truss Steel - Robert F. Kennedy Bridge   Planning  $32,114,200 $32,114,200 0% 2019 2019 2023 2023
Throgs Neck Bridge
Painting of the Suspended Span Steel and Tower Base cells - Throgs Neck Bridge   Planning  $23,520,324 $23,520,324 0% 2018 2018 2021 2021
Painting of the Anchorages Interior - Throgs Neck Bridge Construction $8,218,139 $8,218,139 0% Dec 2015 Dec 2015 Jun 2018 Oct 2018
Verrazano-Narrows Bridge
Painting of the Suspended Span Upper and Lower Level Steel - Verrazano-Narrows Bridge   Planning  $40,906,554 $40,906,554 0% 2018 2018 2021 2021
Number of Projects for MTA Bridges & Tunnels = 7